Friday, March 30, 2012

MERALCO Maintenance Schedule for April 2 - 8, 2012 (Grp 2) (Sent by: Janice V. De Asis)

=======================================================================
WELCOME TO MERALCO'S MAINTENANCE SCHEDULE VIA E-MAIL
------------------------------------------------------------------------------------------------------------------

Attached is the schedule of our pre-arranged power interruptions for April
2 to 8, 2012. This serves as a general information guide and should not be
directly construed as an interruption advisory to the e-mail recipients.

Please call us at telephone numbers 16211 or 631-1111 for verification of
power interruption schedule.

If you wish to unsubscribe, please send us an e-mail and type in the word
"Unsubscribe".

Thank you very much.




MAINTENANCE SCHEDULE

To carry out necessary maintenance and upgrading works on various
MERALCO distribution facilities, electric service will be temporarily
interrupted on the following dates and places:


MONDAY, APRIL 2, 2012
CAVITE (TANZA; AND TRECE MARTIREZ CITY)
BETWEEN 9:00AM AND 10:00AM AND THEN BETWEEN 1:00PM AND 2:00PM – THE
WHOLE OF CIRCUIT TMC-1 37XW; AND PORTION OF CIRCUIT TANZA 38ZW
Portion of Tanza – Trece Martirez Highway from near Tradition
Homes in Bgy. Luciano, Trece Martirez City to and including Pabahay
2000, Carissa Homes Subd., Sunrise Place Subd., Belvedere Towne
Subd., Westwood Place Subd., Tres Cruzes Elementary School, Camp
Riego De Dios, Bgys. Bagtas, Paradahan I & II and Tres Cruzes in
Tanza.
City View Subd., Ciudad Pangarap, Metroland Terraces Subd.,
Transville Homes Subd., Capitol Hillls Subd. 1 & 2, Goldcrest Villas;
Bgys. De Ocampo, Inocencio, Lapidario, Luciano and San Agustin in
Trece Martirez City.

REASON: Preventive maintenance and testing works inside Meralco –
Tanza substation.

TUESDAY, APRIL 3, 2012
LAGUNA (SAN PEDRO); AND MUNTINLUPA CITY
BETWEEN 9:00AM AND 9:30AM AND THEN BETWEEN 1:30PM AND 2:00PM –
PORTION OF CIRCUIT SAN PEDRO 425WH
Portion of Magsaysay Road from San Pedro – Biñan National
Highway to HHI Compound including Metromix Batching Plant, Sepphil
Manufacturing, South Luzon Expressway - San Pedro Toll Exit and
United Polyresins in Bgy. San Antonio, San Pedro, Laguna.

BETWEEN 9:00AM AND 2:00PM – PORTIONS OF CIRCUIT SAN PEDRO 425WH
Portion of Magsaysay Road and Victoria Ave. from near HHI
Compound in San Pedro, Laguna to Daang Reyna St. in Muntinlupa City
including Camella Homes Woodhills Subd., Holiday Homes Subd. Phase 2,
La Marea Mansions, La Marea Trails Subd. Phases 1,2 & 3, Reaville
Subd., St. Anne Homes I, Adelina Complex Subd., Carmen Subd., Elnor
Subd., Fiesta Homes Subd., Holiday Hills Subd., Holiday Homes Subd.,
Holiday Park Subd.; Petron Gas Station, McDonald's Restaurant,
Pancake House, Maxitech Manufacturing, Movall Interiors, Dieko
Plastic, TAT Filipinas Golf Club and St. Andrew Ice Plant in Bgy. San
Antonio, San Pedro, Laguna.
Portion of Daang Reyna St. from Victoria Ave. to and including
Camella Ridgeview Subd., Parco Bello Subd., Cristina Homes Subd.,
Victoria Homes – Ruby Park Subd. Diamond Park Subd., Emerald Heights
Subd., Jade Heights Subd. and Sapphire Heights Subd. in Bgy. Tunasan,
Muntinlupa City.
Portion of Narra St. from Magsaysay Road to and including
Colina Subd., Crismor Subd., Filinvest Homes South Peak Subd.,
Parkspring Ville, Parkview Subd., Southville Subd – NHA Subd.;
Sisters of Mary Immaculate School, FVC Phils., Holiday Hills Piggery,
Metal Caps Manufacturing and Bacavalley Power Plant in Bgys. GSIS,
San Antonio and San Vicente in San Pedro, Laguna.

REASON: Reconductoring of primary lines and other maintenance
works along Magsaysay Road in Bgy. San Antonio, San
Pedro, Laguna.

WEDNESDAY, APRIL 4, 2012
CAVITE (IMUS)
BETWEEN 9:00AM AND 9:15AM AND THEN BEWTEEN 1:45PM AND 2:00PM –
PORTION OF IMUS 36WK
Portion of Gen. Emilio Aguinaldo Highway from near Ayala Mall
to and including Dara Subd., Mango Village, Landtrust Homes, Santiago
Subd., Villa Elisa Subd. and Richlane Subd. in Bgys. Anabu II- A, C,
D, E and F; Salitran I, II and IV.

BETWEEN 9:00AM AND 2:00PM – PORTION OF IMUS 36WK
Portion of Gen. Emilio Aguinaldo Highway from RBS Display
Center in Bgy. Anabu II-D to near Ayala Mall including Pallas Athena
Classique Subd. in Bgy. Anabu II-C.

REASON: Relocation of primary facilities along Gen. Emilio
Aguinaldo Highway in Bgy. Anabu II-C, Imus, Cavite.

WEDNESDAY TO THURSDAY, APRIL 4 - 5, 2012
QUEZON CITY (CUBAO)
BETWEEN 11:00PM (WED., 04/04/12) AND 5:00AM (THU., 04/05/12) –
PORTION OF CIRCUIT CUBAO 43VQ
Portion of Gen. McArthur St. from Times Square St. to Araneta
St. including Telus Call Center, Araneta Coliseum and New Farmers
Plaza in Cubao.

REASON: Line reconstruction works affected by the construction of
link bridge along Gen. McArthur corner Gen. Aguinaldo
Sts. in Cubao, Quezon City.

THURSDAY, APRIL 5, 2012
BATANGAS PROVINCE (STO. TOMAS); AND LAGUNA (CALAMBA CITY)
BETWEEN 6:00AM AND 8:00PM – THE WHOLE OF CIRCUITS CIP-2 323SD, 324SD,
325SD AND 326SD; CIPP 311CIP, 312CIP, 313CIP, 315CIP, 323CIP, 326CIP
AND 327CIP; AND FPIP 423WW, 425WW AND 426WW
The whole of Carmelray Industrial Park 2 in Bgy. Punta, Calamba
City, Laguna.
Sunpower Phils., Philip Morris, First Philec, Hoya, WCL Banks 1
& 2 and Leighton in First Philippine Indusrial Park in Bgy. Sta.
Anastacia, Sto. Tomas, Batangas Province.

REASON: Preventive maintenance and testing works inside Meralco –
CIP-2 substation; and cutting in of Meralco CIP-2
substation to new Canlubang – Calamba – CIP-2 and Los
Baños – CIP 2 – FPIP 115kV transmission lines.

LAGUNA (STA. ROSA CITY)
BETWEEN 9:00AM AND 9:30AM AND THEN BETWEEN 2:30PM AND 3:00PM –
PORTION OF CIRCUITS STA. ROSA - 2 44WL AND 422WL
Portion of North Science Ave. from North Main Ave. to and
including Integrated Microelectronics, FCC (Phils.). Laguna Saikai,
Laguna Dai-ichi, Daiho (Phils.) and Honda Parts Mfg. in Laguna
Technopark.

BETWEEN 9:00AM AND 3:00PM – PORTION OF CIRCUITS STA. ROSA - 2 44WL
AND 422WL
Portion of North Science Ave. from East Science Ave. to and
including Hitachi Global Storage Technologies, Moriroku Phils., FRP
Corp., Yutaka Mfg. and Masuda Phils. in Laguna Technopark.
Portion of Technology Ave. from Tokyo Seat Phils. to and
including Kisho Sakata Electronics and Swedish Match Phils. in Laguna
Technopark.

REASON: Line reconstruction works along Technology Ave. in Laguna
Technopark, Sta. Rosa City, Laguna.

FRIDAY, APRIL 6, 2012
CAVITE (CARMONA)
BETWEEN 9:00AM AND 5:00PM – THE WHOLE OF CIRCUIT LIIP 65WM
ROHM Electronics in People's Technology Complex.

REASON: Preventive maintenance and testing works inside Meralco –
LIIP substation.

SATURDAY, APRIL 7, 2012
MANDALUYONG CITY
BETWEEN 9:00AM AND 3:00PM – PORTION OF CIRCUIT SM–SHANGRI-LA 44VR
San Miguel Bldg. in Bgy. Wack – Wack Greehills East.

REASON: Replacement of poles and conversion from secondary
compecsated metering to primary metering of San Miguel
Corporation in Bgy. Wack – Wack Greehills East,
Mandaluyong City.

PASAY CITY
BETWEEN 9:00AM AND 4:00PM – PORTION OF CIRCUIT PASAY 27U
Portion of M. Dela Cruz St. near Paquita St. including Ibay
Commercial Bldg. in San Roque.

REASON: Relocation of facilities along M. Dela Cruz St. in San
Roque, Pasay City.




MERALCO exerts all efforts to restore electric service as scheduled.
However, there are instances when due to unavoidable circumstances,
restoration may extend beyond the published schedule.
For more information, please contact our CALL CENTER at telephone
nos. 16211 / 631-1111, fax nos. 1622-8554 / 1622-8556, or e-mail address
callcenter.tech.assist@meralco.com.ph. For faster resolution of inquiries,
please use the Bill ID Number or Service Identification Number (SIN)
indicated in your electric bills.
For those who prefer to receive this schedule via e-mail, simply
write to us at callcenter.tech.assist@meralco.com.ph and type in the phrase
"Request for weekly schedule".




VIEW YOUR BILL ON LINE. VISIT OUR WEBSITE!
www.meralco.com.ph



Privileged/Confidential information contained in this e-mail and its attachment/s is intended solely for the use of the addressee and is not meant for reproduction, disclosure and distribution to others without previous authorization from Meralco or its authorized representative. If erroneously sent or received, please do not open and delete the same from your system. Unless, otherwise specifically stated and confirmed by the authorized representative of Meralco, the opinions and views that may be contained therein are personal to the sender.

Friday, March 23, 2012

MERALCO Maintenance Schedule for March 26 - April 1, 2012 (Grp2) (Sent by: Janice V. De Asis)

=======================================================================
WELCOME TO MERALCO'S MAINTENANCE SCHEDULE VIA E-MAIL
------------------------------------------------------------------------------------------------------------------

Attached is the schedule of our pre-arranged power interruptions for March
26 to April 1, 2012. This serves as a general information guide and should
not be directly construed as an interruption advisory to the e-mail
recipients.

Please call us at telephone numbers 16211 or 631-1111 for verification of
power interruption schedule.

If you wish to unsubscribe, please send us an e-mail and type in the word
"Unsubscribe".

Thank you very much.




MAINTENANCE SCHEDULE

To carry out necessary maintenance and upgrading works on various
MERALCO distribution facilities, electric service will be temporarily
interrupted on the following dates and places:


SUNDAY, MARCH 25, 2012
LAGUNA (LOS BAÑOS)
BETWEEN 7:00AM AND 8:00AM AND THEN BETWEEN 6:00PM AND 7:00PM – THE
WHOLE OF CIRCUIT LOS BAÑOS 31WT
Portion of PNR Railroad Track and San Luis St. from near Los
Baños - Bay National Road to and including Dairyville Subd., Pleasant
Village, Hillside Subd., L. A. Village, Bos. Buot and Putho -
Tuntungin.
Portion of Silangan Groove from near International Rice
Research Institute to Lopez Ave. in Bo. San Antonio.

REASON: Preventive maintenance and testing works inside NGCP –
Los Baños substation.

BULACAN (MEYCAUAYAN)
BETWEEN 9:00AM AND 9:30AM AND THEN BETWEEN 2:00PM AND 2:30PM –
PORTION OF CIRCUIT MEYCAUAYAN 42YM
Portion of Iba Road from North Luzon Expressway to and
including Sto. Niño Homes Phase II, Mt. Carmel Subd., Emco Subd., Ana
Maria Subd., Meridian Industrial Park and Sterling Industrial Park in
Bgys. Calvario, Pandayan, Iba and Pantoc.

BETWEEN 9:00AM AND 2:30PM – PORTION OF CIRCUIT MEYCAUAYAN 42YM
The whole of Muralla Industrial Subd. in Bgy. Perez.

REASON: Various maintenance works at Muralla Industrial Subd. in
Bgy. Perez, Meycauayan, Bulacan.

SUNDAY TO MONDAY, MARCH 25 – 26, 2012
VALENZUELA CITY
BETWEEN 11:00PM AND 11:59PM (SUN., 03/25/12) – PORTIONS OF CIRCUIT
MALINTA 48YB
Portion of McArthur Highway from Meralco – Malinta substation
near Maysan Road to near J. Marcelo St. including Poblacion II Road,
Daez, San Vicente Sts., Concepcion Compound, Pag-asa 2 Subd.; South
Supermarket, McDonald's Restaurant, Mercury Drug, Valenzuela
Municipal Hall, Valenzuela Legislative and Executive Bldg., Unifive
Steel, Valenzuela City Hall of Justice, First Interpack
Manufacturing, Caltex Gas Station, PNB, Telecommunication Training
Institute, NBI Valenzuela, Valenzuela PESO Office, BDO, Parish of the
Holy Family, SSS Valenzuela Branch, BPI, Wonder Box Makers and
Bayantel in Bgys. Malinta and Karuhatan.
Portion of A. Pablo St. from McArthur Highway to A. De Castro
St. including A. Lopez Compound, Karuhatan Townhomes; and La Suerte
Manufacturing in Bgys. Malinta and Karuhatan.
Portion of Gen. T. De Leon St. (T. Bugallon) from Padrigal St.
to Policarpio St. including A. Padrinao, Perez, Sts., M. Salvador
Compound II, Clemente Compound, Teacher's Compound, Gumamela Complex
Compound, Arbor Towne Subd. Phases 1, 3 & 4, Deato Subd., Galguiera
Compound, Fortune Village Phases 1 & 2, Prodon Subd. Phases 1 & 2,
Santos Subd., Tañada Subd.; Valenzuela General Hospital, Star Ace
Lumber, LTO Valenzuela, Solid Century, Seahorse Industrial, Cardinal
Plastics, Daimaru Plastics, Wallert Compound and ROCA Manufacturing
in Bgys. Karuhatan and Gen. T. De Leon.

BETWEEN 11:00PM (SUN., 03/25/12) AND 5:00AM (MON., 03/26/12) –
PORTION OF CIRCUIT MALINTA 48YB
Portion of Gen. T. De Leon St. (T. Bugallon) from Arty Subd.
Phase 4 to near Padrigal St. including Milestone Subd.; and Reyes
Haircutter Salon in Bgy. Karuhatan.
Portion of Bible St. from Gen. T. De Leon St. (T. Bugallon) to
and including Febias College of Bible Compound, Biblical Seminary of
the Philippines and WE Enterprises in Bgy. Karuhatan.

REASON: Replacement of rotten wood poles, relocation of
facilities and other maintenance works along Gen. T. De
Leon St. in Bgy. Karuthatan, Valenzuela City.

TUESDAY, MARCH 27, 2012
CAVITE (BACOOR; AND IMUS)
BETWEEN 9:00AM AND 9:30AM AND THEN BETWEEN 1:30PM AND 2:00PM –
PORTION OF CIRCUIT BACOOR 410WX
Portion of Palico Road from Gen. Emilio Aguinaldo Highway to
near Imus – Bacoor Municipal boundary in Bgy. Palico IV, Imus.

BETWEEN 9:00AM AND 2:00PM – PORTION OF CIRCUIT BACOOR 410WX
Meadowood Executive Village and Vita Toscana in Bgy. Niog II
and Bacoor town proper.

REASON: Line reconductoring works along Meadowood Ave. in
Meadowood Executive Village, Bacoor town proper.

WEDNESDAY TO THURSDAY, MARCH 28 - 29, 2012
QUEZON CITY (CUBAO)
BETWEEN 11:30PM AND 11:59PM (WED., 03/28/12) AND THEN BETWEEN 5:00AM
AND 5:30AM (THU., 03/29/12) – PORTION OF CIRCUIT CUBAO 48VQ
Portion of Main Ave. from 13th Ave to Epifanio Delos Santos
Ave. (EDSA) including 5th, 7th, 8th, 9th, 10th, 11th and 12th Aves.;
Roosevelt Memorial High School, Shell Gas Station, SM Hypermarket and
Iglesia Ni Cristo in Bgy. Socorro.

BETWEEN 11:30PM (WED., 03/28/12) AND 5:30AM (THU., 03/29/12) –
PORTION OF CIRCUIT CUBAO 48VQ
Portion of Epifanio Delos Santos Ave. (EDSA) from near Main
Ave. to and including AFPSLAI Bldg.; Liberty and 6th Aves. in Bgy.
Socorro.

REASON: Replacement of rotten pole and cross-arm along Epifanio Delos
Santos Ave. (EDSA) cor. Bonny Serran St. in Bgy. Socorro,
Quezon City.

THURSDAY, MARCH 29, 2012
LAGUNA (SAN PEDRO); AND MUNTINLUPA CITY
BETWEEN 9:00AM AND 9:30AM AND THEN BETWEEN 1:30PM AND 2:00PM –
PORTION OF CIRCUIT SAN PEDRO 425WH
Portion of Magsaysay Road from San Pedro – Biñan National
Highway to HHI Compound including Metromix Batchning Plant, Sepphil
Manufacturing, South Luzon Expressway - San Pedro Toll Exit and
United Polyresins in Bgy. San Antonio, San Pedro, Laguna.

BETWEEN 9:00AM AND 2:00PM – PORTIONS OF CIRCUIT SAN PEDRO 425WH
Portion of Magsaysay Road and Victoria Ave. from near HHI
Compound in San Pedro, Laguna to Daang Reyna St. in Muntinlupa City
including Camella Homes Woodhills Subd., Holiday Homes Subd. Phase 2,
La Marea Mansions, La Marea Trails Subd. Phases 1,2 & 3, Reaville
Subd., St. Anne Homes I, Adelina Complex Subd., Carmen Subd., Elnor
Subd., Fiesta Homes Subd., Holiday Hills Subd., Holiday Homes Subd.,
Holiday Park Subd.; Petron Gas Station, McDonald's Restaurant,
Pancake House, Maxitech Manufacturing, Movall Interiors, Dieko
Plastic, TAT Filipinas Golf Club and St. Andrew Ice Plant in Bgy. San
Antonio, San Pedro, Laguna.
Portion of Daang Reyna St. from Victoria Ave. to and including
Camella Ridgeview Subd., Parco Bello Subd., Cristina Homes Subd.,
Victoria Homes – Ruby Park Subd. Diamond Park Subd., Emerald Heights
Subd., Jade Heights Subd. and Sapphire Heights Subd. in Bgy. Tunasan,
Muntinlupa City.
Portion of Narra St. from Magsaysay Road to and including
Colina Subd., Crismor Subd., Filinvest Homes South Peak Subd.,
Parkspring Ville, Parkview Subd., Southville Subd – NHA Subd.;
Sisters of Mary Immaculate School, FVC Phils., Holiday Hills Piggery,
Metal Caps Manufacturing and Bacavalley Power Plant in Bgys. GSIS,
San Antonio, San Vicente in San Pedro, Laguna.

REASON: Reconductoring of primary lines and other maintenance works
along Magsaysay Road in Bgy. San Antonio, San Pedro, Laguna.

SATURDAY, MARCH 31, 2012
RIZAL (ANTIPOLO CITY)
BETWEEN 9:00AM AND 2:00PM – PORTION OF CIRCUIT DOLORES 42XM
Portion of Circumferential Road from P. Oliveros St. to near
Adarna St. including Merville Park Subd.; Bonoan Bldg., Rizal
Provincial Capitol and Ynares Center in Bgy. San Roque.
Portion of P. Oliveros St. from Circumferential Road to and
including Flying V Gas Station in Bgy. Dela Paz.

REASON: Installation of primary lines along P. Oliveros St. in Bgy.
Dela Paz, Antipolo City, Rizal.

SUNDAY, APRIL 1, 2012
BULACAN (NORZAGARAY; AND SAN JOSE DEL MONTE CITY)
BETWEEN 5:00AM AND 6:00AM AND THEN BETWEEN 3:00PM AND 4:00PM – THE
WHOLE OF CIRCUITS SAPANG PALAY 33YO AND 34YO
Portion of Ipo Road and Minuyan Provincial Road from Newton
Drive in Bgy. Minuyan II, San Jose Del Monte City to Ipo Dam
including Hulo, Sapang Saging, Alinsangan, Crusher, Obrero, Sapang
Kawayan, Malaganit Sts., Minuyan, Curbada Roads; Marlane Subd. and
Sunnyfield Subd. in Bgys. San Mateo, Bigte, Minuyan, Matictic and
Bitungol in Norzagaray; Quarry St.; Bgys. Minuyan II, III & IV and
Minuyan proper in San Jose Del Monte City.
Portion of Bagong Buhay Provincial Road, Sulucan and Matandang
Barrio Roads from Minuyan Road to and including Lingunan St. in Bgys.
Partida and Tigbe in Norzagaray; J. P. Rizal, Pres. Quirino, San
Miguel, and San Vicente Sts. in Bgys. San Rafael I, III, IV & V,
Fatima II & IV, Santa Cruz and Sto. Niño II in San Jose Del Monte
City.

BETWEEN 6:00AM AND 12:00NN – THE WHOLE OF CIRCUIT SAPANG PALAY 32YO
Portion of Quirino Highway, Igay Road and Kaybangan Road from
Towerville Drive to and including Bgy. San Isidro; Palmera Northwinds
City, North Hills Subd., Northridge Royale, Northridge Executive,
Northridge Prime Estate, North Gate Park, Tierra del Sueño Heights,
Towerville, City Homes, NS Salvador Marble, San Jose Water District,
Carissa Homes North 1 & 2B and Paradise III; Bgys. Kaybangan,
Kaypian, Minuyan Proper, San Roque, Sto. Cristo and Tungkong Mangga
in San Jose Del Monte.

REASON: Preventive maintenance and testing works inside Meralco –
Sapang Palay substation.

PASIG CITY (PINAGBUHATAN)
BETWEEN 9:00AM AND 3:00PM – THE WHOLE OF CIRCUIT TAGUIG 45ZL
Republic Asahi Glass Compound in Bgy. Pinagbuhatan.

REASON: Preventive maintenance and testing works inside Meralco –
Taguig substation.

LAGUNA (STA. ROSA)
BETWEEN 9:00AM AND 9:30AM AND THEN BETWEEN 2:30PM AND 3:00PM –
PORTION OF CIRCUITS STA. ROSA - 2 44WL AND 422WL
Portion of North Science Ave. from North Main Ave. to and
including Integrated Microelectronics, FCC (Phils.). Laguna Saikai,
Laguna Dai-ichi, Daiho (Phils.) and Honda Parts Mfg. in Laguna
Technopark.

BETWEEN 9:00AM AND 3:00PM – PORTION OF CIRCUITS STA. ROSA - 2 44WL
AND 422WL
Portion of North Science Ave. from East Science Ave. to and
including Hitachi Global Storage Technologies, Moriroku Phils., FRP
Corp., Yutaka Mfg. and Masuda Phils. in Laguna Technopark.
Portion of Technology Ave. from Tokyo Seat Phils. to and
including Kisho Sakata Electronics and Swedish Match Phils. in Laguna
Technopark.

REASON: Line reconstruction works along Technology Ave. in Laguna
Technopark, Sta. Rosa, Laguna.




MERALCO exerts all efforts to restore electric service as scheduled.
However, there are instances when due to unavoidable circumstances,
restoration may extend beyond the published schedule.
For more information, please contact our CALL CENTER at telephone
nos. 16211 / 631-1111, fax nos. 1622-8554 / 1622-8556, or e-mail address
callcenter.tech.assist@meralco.com.ph. For faster resolution of inquiries,
please use the Bill ID Number or Service Identification Number (SIN)
indicated in your electric bills.
For those who prefer to receive this schedule via e-mail, simply
write to us at callcenter.tech.assist@meralco.com.ph and type in the phrase
"Request for weekly schedule".




VIEW YOUR BILL ON LINE. VISIT OUR WEBSITE!
www.meralco.com.ph




Privileged/Confidential information contained in this e-mail and its attachment/s is intended solely for the use of the addressee and is not meant for reproduction, disclosure and distribution to others without previous authorization from Meralco or its authorized representative. If erroneously sent or received, please do not open and delete the same from your system. Unless, otherwise specifically stated and confirmed by the authorized representative of Meralco, the opinions and views that may be contained therein are personal to the sender.

Friday, March 16, 2012

MERALCO Maintenance Schedule for March 19 - 25, 2012 (Grp2) (Sent by: Janice V. De Asis)

=======================================================================
WELCOME TO MERALCO'S MAINTENANCE SCHEDULE VIA E-MAIL
------------------------------------------------------------------------------------------------------------------

Attached is the schedule of our pre-arranged power interruptions for March
19 to 25, 2012. This serves as a general information guide and should not
be directly construed as an interruption advisory to the e-mail recipients.

Please call us at telephone numbers 16211 or 631-1111 for verification of
power interruption schedule.

If you wish to unsubscribe, please send us an e-mail and type in the word
"Unsubscribe".

Thank you very much.




MAINTENANCE SCHEDULE

To carry out necessary maintenance and upgrading works on various
MERALCO distribution facilities, electric service will be temporarily
interrupted on the following dates and places:


TUESDAY, MARCH 20, 2012
CAVITE (SILANG)
BETWEEN 9:00AM AND 1:00PM – PORTION OF CIRCUIT TAGAYTAY 32XS
Rancho Imperial Subd. and Tagaytay Meridian Subd. in Bgy.
Tartaria.

REASON: Replacement of rotten cross-arms and conductors in
Meridian Subd., Bgy. Tartaria, Silang , Cavite.

TUESDAY TO WEDNESDAY, MARCH 20 - 21, 2012
LAS PIÑAS CITY
BETWEEN 9:00PM AND 9:30PM (TUE., 03/20/12) AND THEN BETWEEN 3:30AM
AND 4:00AM (WED., 03/21/12) – PORTIONS OF CIRCUIT LAS PIÑAS 45XA
Portion of Quirino Ave. from near Golden Haven Memorial Park to
and including Villa Fidela Subd. in Bgys. Pulang Lupa I and Elias
Aldana.
Portion of Quirino Ave. and Tramo Road from near A. Bonifacio
St. to and including St. Joseph Academy, New Creation Manufacturing;
San Jose St., Aldana Ave.; Casimiro Townhomes, Citihomes I Subd. and
Jaleville Subd. in Bgys. Daniel Fajardo and Manuyo I.
Portion of Coastal Road from Our Lady of Peace Hospital to and
including Coastal Plaza Condominium and Public Estate Authority's
Multi-Residential Buildings in Bgys. Elias Aldana, Daniel Fajardo and
San Dionisio.

BETWEEN 9:00PM (TUE., 03/20/12) AND 4:00AM (WED., 03/21/12) – PORTION
OF CIRCUIT LAS PIÑAS 45XA
Portion of Quirino Ave. and San Francisco St. from near GSIS
Family Bank to and including All Nations Food City in Bgys. Elias
Aldana and Daniel Fajardo.

REASON: Replacement of rotten wood pole and other maintenance
works along San Francisco St., Bgy. Daniel Fajardo, Las
Piñas City.

LAGUNA (CABUYAO; AND STA. ROSA)
BETWEEN 11:00PM AND 11:30PM (TUE., 03/20/12) AND THEN BETWEEN 3:30AM
AND 4:00AM (WED., 03/21/12) – PORTIONS OF CIRCUIT BALIBAGO 45XV
Portion of Sta. Rosa – Cabuyao National Highway from Rizal
Blvd. to near Shell Gas Station including Villa Caceres in Poblacion.
Portion of Sta. Rosa – Cabuyao National Highway from near La
Hoya De Sta. Rosa Subd. to and including Shineland Village, C. T.
Limcaoco Subd., El Sol Subd., Nuestra de Carmen Subd., Vanessa Homes
Subd., Bella Solana 1, 2, 3,& 4, Cabuyao Major Homes, Stoneridge
Ville, Tierra El Sol, St. Joseph Village 4, 5, 6, 7 & 8, Celestine
Homes Subd., Maripaz Ville Subd., Sunrise Village I; Bgys. Bigaa,
Butong, Poblacion, Marinig, Niugan and Sala in Cabuyao; Southville 3
Resettlement, Naja Ville Subd., South Drive Ville, Anahaw Homes
Subd., Console Subd. Phase 4 & 5, Mariwuita Pueblo Subd. I & II,
Panoramaville Subd., Robes Francisco Subd., Solcar Ville, Sta. Rosa
Homes Ville, Terracon Homes VI, Villa Anthurium, Golden City Subd.
Phase IA, IB, IB-1, IC, ID, 2A, 2B, 2B-1, 2C, 2D, 3C, 4A, 4B, 4D &
4E, Mabuhay Homes 2000 Phase 1E, 2E & 2F; Bgys. Caingin, Dila, Dita,
Pook and Poblacion in Sta. Rosa.

BETWEEN 11:00PM (TUE., 03/20/12) AND 4:00AM (WED., 03/21/12) –
PORTIONS OF CIRCUIT BALIBAGO 45XV
Sta. Rosa Commercial Complex in Bgy. Balibago.
Portion of Sta. Rosa – Cabuyao National Highway from near Shell
Gas Station to near La Hoya De Sta. Rosa Subd. in Bgy. Balibago.

REASON: Replacement of rotten pole near La Hoya De Sta. Rosa; and
replacement of rotten cross-arm and lightning arresters
at Balibago Commercial Complex, Sta. Rosa, Laguna.

MAKATI CITY
BETWEEN 11:00PM AND 11:30PM (TUE., 03/20/12) AND THEN BETWEEN 5:00AM
AND 5:30AM (WED., 03/21/12) – PORTION OF CIRCUIT URDANETA 45VS
Portion of Sedeno St. from Paseo De Roxas St. to Valero St.
including PS Bank Center Bldg. and 88 Corporate Center Bldg. in
Salcedo Village, Bgy. Bel-Air.

BETWEEN 11:00PM (TUE., 03/20/12) AND 5:30AM (WED., 03/21/12) –
PORTION OF CIRCUIT URDANETA 45VS
Portion of Paseo De Roxas St. from China Bank Bldg. to Sedeno
St. including BA Lepanto Bldg., Equitable Bank Tower, Philcom Bldg.
and Paseo Center in Salcedo Village, Bgy. Bel-Air.
Portion of Valero St. from Sedeno St. to and including Valero
Carpark II Bldg. in Salcedo Village, Bgy. Bel-Air.
Portion of San Agustin St. from Valero Plaza to H. V. Dela
Costa St. including Gammon Center, Vernida IV Cosmopolitan Tower
Condominium, The Cordova, One Lafayette Square, Liroville
Condominium, The Pearl Bank Center, CCH Bldg., Alpap I Bldg., Paseo
Parkview Tower, Centrum II Condominium, Antel Platinum Tower, Alfaro
Place, Grand Tower, Eurovilla III Bldg., Manhattan Square Bldg.,
Tiffany Court, Anthenaeum, The Forbes Tower and Liberty Center Bldg.
in Salcedo Village, Bgy. Bel-Air.

REASON: Installation of new primary line switch and line
rehabilitation works along San Agustin, Villar and Valero
Sts. in Salcedo Village, Makati City.

WEDNESDAY TO THURSDAY, MARCH 21 – 22, 2012
VALENZUELA CITY
BETWEEN 11:00PM AND 11:59PM (WED., 03/21/12) – PORTIONS OF CIRCUIT
MALINTA 48YB
Portion of McArthur Highway from Meralco – Malinta substation
near Maysan Road to near J. Marcelo St. including Poblacion II Road,
Daez, San Vicente Sts., Concepcion Compound, Pag-asa 2 Subd.; South
Supermarket, McDonald's Restaurant, Mercury Drug, Valenzuela
Municipal Hall, Valenzuela Legislative and Executive Bldg., Unifive
Steel, Valenzuela City Hall of Justice, First Interpack
Manufacturing, Caltex Gas Station, PNB, Telecommunication Training
Institute, NBI Valenzuela, Valenzuela PESO Office, BDO, Parish of the
Holy Family, SSS Valenzuela Branch, BPI, Wonder Box Makers and
Bayantel in Bgys. Malinta and Karuhatan.
Portion of A. Pablo St. from McArthur Highway to A. De Castro
St. including A. Lopez Compound, Karuhatan Townhomes; and La Suerte
Manufacturing in Bgys. Malinta and Karuhatan.
Portion of Gen. T. De Leon St. (T. Bugallon) from Padrigal St.
to Policarpio St. including A. Padrinao, Perez, Sts., M. Salvador
Compound II, Clemente Compound, Teacher's Compound, Gumamela Complex
Compound, Arbor Towne Subd. Phases 1, 3 & 4, Deato Subd., Galguiera
Compound, Fortune Village Phases 1 & 2, Prodon Subd. Phases 1 & 2,
Santos Subd., Tañada Subd.; Valenzuela General Hospital, Star Ace
Lumber, LTO Valenzuela, Solid Century, Seahorse Industrial, Cardinal
Plastics, Daimaru Plastics, Wallert Compound and ROCA Manufacturing
in Bgys. Karuhatan and Gen. T. De Leon.

BETWEEN 11:00PM (WED., 03/21/12) AND 5:00AM (THU., 03/22/12) –
PORTION OF CIRCUIT MALINTA 48YB
Portion of Gen. T. De Leon St. (T. Bugallon) from Arty Subd.
Phase 4 to near Padrigal St. including Milestone Subd.; and Reyes
Haircutter Salon in Bgy. Karuhatan.
Portion of Bible St. from Gen. T. De Leon St. (T. Bugallon) to
and including Febias College of Bible Compound, Biblical Seminary of
the Philippines and WE Enterprises in Bgy. Karuhatan.

REASON: Replacement of rotten wood poles, relocation of
facilities and other maintenance works along Gen. T. De
Leon St. in Bgy. Karuthatan, Valenzuela City.

PASIG CITY
BETWEEN 11:30PM AND 11:59PM (WED., 03/21/12) AND THEN BETWEEN 5:00AM
AND 5:30AM (THU., 03/22/12) – PORTION OF CIRCUITS SM SHANGRI-LA 45VR
AND 51VR
Portion of San Miguel Ave. from near Lourdes St. to and
including Pacific Center and Medical Plaza – Ortigas Building in Bgy.
San Antonio.
Portion of Meralco Ave. from Doña Julia Vargas Ave. to and
including Gen. Atienza, St. Paul Sts.; St. Paul College, Department
of Education Complex, The Alexandra, Renaissance 1000, Renaissance
2000, Renaissance 3000, Benpres Bldg., Ortigas Home Depot and MWSS
Pasig Pumping Station and Reservoir in Bgys. San Antonio and Ugong.

BETWEEN 11:30PM (WED., 03/21/12) AND 5:30AM (THU., 03/22/12) –
PORTION OF CIRCUIT SM SHANGRI-LA 45VR
Portion of San Miguel Ave. from Exchange Road (Tektite Road) to
and including One Magnificent Mile (OMM) Citra Building in Bgy. San
Antonio.

REASON: Line reconstruction works along San Miguel Ave. and
Exchange Road in Bgy. San Antonio, Pasig City.

THURSDAY, MARCH 22, 2012
QUEZON CITY
BETWEEN 9:00AM AND 3:00PM – PORTION OF CIRCUIT DILIMAN 425VU
Portion of Don Mariano Marcos Ave. (Commonwealth) from Imelda
Road to Doña Carmen Ave. including Adarna, Bicoleyte, Bato – Bato,
Don Fabian, Ecols, Emerald, Gold, Jasmin, Kilyawan, Mango, Martan,
Martinez, Pipit, Rose, San Bartolome, San Diego, San Isidro, San
Miguel, San Pascual, San Pedro, San Simon, Sta. Maria, Steve, Sto.
Domingo, Sto. Rosario, Tabigo Sts., Riverside Homesite Units IV & V,
National Government Center ROW Housing Project, Don Jose Subd., Don
Fabian Subd., Ideal Subd.; Jollibee – Villongco, Chowking -
Villongco, Rotary Soup Kitchen Foundation, Commonwealth High School
and Polytechnic University of the Philippines – Commonwealth Campus
in Bgys. Commonwealth, Holy Spirit and Sto. Niño.

REASON: Replacement of broken concrete pole and relocation of
primary facilities affected by DPWH road widening project
along Don Mariano Marcos Ave. (Commonwealth) in Bgy.
Commonwealth, Quezon City.

THURSDAY TO FRIDAY, MARCH 22 – 23, 2012
LAGUNA (STA. CRUZ)
BETWEEN 11:00PM (THU., 03/22/12) AND 4:00AM (FRI., 03/23/12) –
PORTION OF CIRCUITS SAN PABLO 42WJ – STA. CRUZ 421WF; AND STA. CRUZ
322WF – 32WF
Portion of Pila – Sta. Cruz National Highway from near Celino
Subd. in Bgy. Duhat to and including Asiablooms Hotel and Sunstar
Mall in Bgys. Patimbao, Gatid, Bagumbayan, Labuin and Bubukal.

REASON: Relocation of primary facilities affected by DPWH road
widening project along Pila – Sta. Cruz National Highway
in Sta. Cruz, Laguna.

FRIDAY TO SATURDAY, MARCH 23 - 24, 2012
MANDALUYONG CITY (HIGHWAY HILLS)
BETWEEN 11:00PM (FRI., 03/23/12) AND 5:00AM (SAT., 03/24/12) –
PORTION OF CIRCUIT TAGUIG 48ZL
Portion of Reliance St. from Pioneer to Mayflower Sts.
including Commonwealth – Fibisco Division, Mister Donut Commissary,
United Laboratories Warehouse and Focus Enterprises.
Portion of Sheridan St. from Pacific Glass to and including
United Laboratories – Admin Offices and Warehouses and Manufacturing
Plant, Cathedral of the King and Belman I Compound.

REASON: Relocation of facilities along Reliance St. in Bgy.
Highway Hills, Mandaluyong City.

SATURDAY, MARCH 24, 2012
MANILA
BETWEEN 8:00AM AND 8:30AM AND THEN BETWEEN 12:30PM AND 1:00PM –
PORTIONS OF CIRCUIT BINONDO 45N
Portion of Madrid St. from Lavezares St. to Clavel St.
including Barcelona, Sevilla, Oportunidad and Peñarubia Sts. in San
Nicolas.
Portion of Asuncion St. from Claro M. Recto Ave. to Padre Rada
St. including Zaragoza, Elcano Sts.; and MWSS Pumping Station in
Tondo.
Portion of Zaragoza St. from Asuncion St. to near Mabuhay St.
including Balagtas, Kagitingan, Lakandula, Lualhati, Maria Payo,
Masikap, Matiisin, Matimtiman, P. Herrera, Paghanapin, Pitimini, Sgt.
Mabagos and Zabala Sts. in Tondo.
Portion of Del Pan St. from Zaragoza St. to and including Gat
Andres Bonifacio Memorial Hospital in Tondo.

BETWEEN 8:00AM AND 1:00PM – PORTION OF CIRCUIT BINONDO 45N
Portion of Lavezares St. from Camba St. to Elcano St. including
Caballeros St.; and Buen Asenco Bldg. in San Nicolas.
Portion of Camba St. from San Nicolas St. to Claro M. Recto
Ave. including Peñarubia, A. Velasquez, M. De Santos Sts.; Dual Tech
Training Center and Tiu Tian Bldg. in San Nicolas.

REASON: Line reconstruction works along Camba St. in Tondo,
Manila.

SUNDAY, MARCH 25, 2012
MARIKINA CITY
BETWEEN 12:01PM AND 1:00PM – THE WHOLE OF CIRCUIT MELI 18XB
Portion of Jacinto, W. Dela Paz and Florencio Paz Sts. from V.
Santos St. to I. Mendoza St. including P. Dela Paz St.; Sta. Elena
High School and PNB in Bgy. Sta. Elena.
Portion of E. Dela Paz, J. P. Rizal and Gen. Santos Sts. from
Kapt. Moy St. to Marcos Highway including Kapt. Moy, J. P. Laurel,
Sta. Ana, Nicanor Roxas, M. Roxas, J.M. Baesa, M.H. Del Pilar,
Calderon Sts., Shoe Ave.; San Roque Elementary School, Shell Gas
Station, Chinatrust Bank, San Roque Elementary School and Calumpang
Barangay Hall in Bgys. San Roque and Calumpang.
Portion of Mayor Gil Fernando (Angel Tuazon) Ave. from Marikina
East Subd. to and including Midtown Subds. I, II & III in Bgy. San
Roque.

REASON: Preventive maintenance and testing works inside Meralco -
Meli substation.




MERALCO exerts all efforts to restore electric service as scheduled.
However, there are instances when due to unavoidable circumstances,
restoration may extend beyond the published schedule.
For more information, please contact our CALL CENTER at telephone
nos. 16211 / 631-1111, fax nos. 1622-8554 / 1622-8556, or e-mail address
callcenter.tech.assist@meralco.com.ph. For faster resolution of inquiries,
please use the Bill ID Number or Service Identification Number (SIN)
indicated in your electric bills.
For those who prefer to receive this schedule via e-mail, simply
write to us at callcenter.tech.assist@meralco.com.ph and type in the phrase
"Request for weekly schedule".




VIEW YOUR BILL ON LINE. VISIT OUR WEBSITE!
www.meralco.com.ph



Privileged/Confidential information contained in this e-mail and its attachment/s is intended solely for the use of the addressee and is not meant for reproduction, disclosure and distribution to others without previous authorization from Meralco or its authorized representative. If erroneously sent or received, please do not open and delete the same from your system. Unless, otherwise specifically stated and confirmed by the authorized representative of Meralco, the opinions and views that may be contained therein are personal to the sender.

Friday, March 9, 2012

MERALCO Maintenance Schedule for March 12 - 18, 2012 (Grp2) (Sent by: Janice V. De Asis)

=======================================================================
WELCOME TO MERALCO'S MAINTENANCE SCHEDULE VIA E-MAIL
------------------------------------------------------------------------------------------------------------------

Attached is the schedule of our pre-arranged power interruptions for March
12 to 18, 2012. This serves as a general information guide and should not
be directly construed as an interruption advisory to the e-mail recipients.

Please call us at telephone numbers 16211 or 631-1111 for verification of
power interruption schedule.

If you wish to unsubscribe, please send us an e-mail and type in the word
"Unsubscribe".

Thank you very much.




MAINTENANCE SCHEDULE

To carry out necessary maintenance and upgrading works on various
MERALCO distribution facilities, electric service will be temporarily
interrupted on the following dates and places:


MONDAY, MARCH 12, 2012
CAVITE (ALFONSO; AND GEN. AGUINALDO)
BETWEEN 10:00AM AND 3:00PM – PORTION OF CIRCUIT TAGAYTAY WEST 315TGW
Portion of Alfonso – Marahan and Matagbak Roads from near
Alfonso Municipal Hall in Alfonso town proper to and including Bgys.
Sinaliw Malaki, Matagbak I & II, Santa Teresa and Marahan I & II in
Alfonso.
Portion of Sinaliw – Narvaez Road from Matagbak Road to and
including Bgys. Kaymisas, A. Dalusag and Narvaez in Gen. Aguinaldo.

REASON: Line reconductoring works along Alfonso – Marahan Road in
Alfonso, Cavite.

TUESDAY, MARCH 13, 2012
MANILA (TONDO)
BETWEEN 1:01AM AND 2:00AM – THE WHOLE OF CIRCUIT PALOMAR 15L
Portion of C. M. Recto Ave. from Antonio Rivera St. to near
Sto. Cristo St. including C. La Torre and P. Algue Sts.
Portion of Carmen Planas St. from C. M. Recto Ave. to Lakandula
St. including P. Rada, Bilbao, Alburquerque, Asuncion and Ylaya Sts.;
Mang Inasal Restaurant, Jollibee – Tondo and 7- 11 Store.
Portion of Morga St. from Juan Luna St. to Camba St. including
J. Nolasco, Ylaya, Soliman, Asuncion, San Ramon, Abad Santos, Wagas
and Sandico Sts.; Western Police Station 2, Isabelo Delos Reyes
Elementary School and Tondo Fire Department.

REASON: Preventive maintenance and testing works inside Meralco
–Palomar substation.

BULACAN PROVINCE (BOCAUE; BULACAN; AND GUIGUINTO)
BETWEEN 12:01AM AND 12:30AM AND THEN BETWEEN 4:30AM AND 5:00AM –
PORTION OF CIRCUIT STA. MARIA 42YU
Portion of Mercado and Matungao Sts. from near McArthur Highway
in Bgy. Tuktukan, Guiguinto to Camino Real St. in Bgy. Poblacion,
Bulacan including Miraverde and RIS Cpd.; Bgys. Tuktukan, Tabe,
Panginay and Poblacion in Guiguinto; Triple Junction Subd., Villa
Sofia Subd. and Camella Communities in Bgys. Matungao and San Jose in
Bulacan.
Portion of San Nicolas St. in Bgy. Poblacion to and including
Bgys. Pitpitan, Maysantol, Tibig, Balubad, San Francisco and San
Nicolas in Bulacan.

BETWEEN 12:01AM AND 5:00AM – PORTION OF CIRCUIT STA. MARIA 42YU
Portion of Bagumbayan, Daang Bato, Perez and Sabana Sts. from
Camino Real St. in Bgy. Poblacion to and including Bgys. Perez,
Bagumbayan, Bambang, Sta. Ana, Sta. Ines and Taliptip in Bulacan.

REASON: Line maintenance works in Bgys. Bagumbayan, Bambang,
Perez and Taliptip in Bulacan, Bulacan Province.

MANILA (MALATE)
BETWEEN 8:00AM AND 8:15AM AND THEN BETWEEN 11:45AM AND 12:00NN –
PORTION OF CIRCUIT MALATE 22J
Portion of Singalong, Cong. A. Francisco and Angel Linao (Dart)
Sts. from Kapitan Ticong St. to San Isidro St. including Don Isidro,
Dagonoy, Maligaya and Zapanta Sts.

BETWEEN 8:00AM AND 12:00NN – PORTION OF CIRCUIT MALATE 22J
Portion of San Andres St. from F. T. Benitez St. to Taal St.
including Smith, Meding, A. Linao (Dart) and F. Muñoz Sts.; 7-11
Store, St. Anthony School, BDO and Alberto Dy Ong Bldg.

REASON: Replacement of rotten pole along A. Linao St. (Dart) cor.
San Andres St. in Malate, Manila.

CAVITE (AMADEO; AND INDANG)
BETWEEN 9:00AM AND 2:00PM – PORTION OF CIRCUIT SILANG 32WS
Portion of Pangil – Limbon Road from Bgy. Pangil, Amadeo to
Amadeo – Indang Municipal boundary in Bgy. Limbon, Indang.

REASON: Replacement of leaning pole and relocation of primary
lines along Pangil – Limbon Road in Bgy. Pangil, Amadeo,
Cavite.

QUEZON PROVINCE (SAN ANTONIO; AND TIAONG)
BETWEEN 10:00AM AND 1:00PM – THE WHOLE OF CIRCUIT TIAONG 11WE
Portion of Tiaong – San Antonio Municipal Road from Meralco –
Tiaong Substation in Bgy. San Agustin, Tiaong to and including Bgys.
Corazon, Briones, Buliran, Callejon, Loob, Magsaysay, Manuel Del
Valle Sr., Pury, Sampaguita, San Jose, Sinturisan and Poblacion in
San Antonio; Bgys. San Agustin and San Jose in Tiaong.

REASON: Preventive maintenance and testing works inside Meralco -
Tiaong substation.

WEDNESDAY, MARCH 14, 2012
CAVITE (TAGAYTAY CITY); AND LAGUNA (CABUYAO)
BETWEEN 9:00AM AND 2:00PM – PORTION OF CIRCUIT TAGAYTAY 34XS
Portion of Tagaytay – Calamba Road from near Hollywood Subd.
in Bgy. Tolentino to and including Tagaytay Highlands, Monte Vista
Subd., Southridge Subd., Tagaytay Southridge Villas II, Development
Academy of the Phils., BLISS Subd., Horizon's Place Tagaytay,
Pilipinas Farm Subd., Villa Cecilia Subd., Crosswinds Subd. and
Palace in the Sky; Bgys. Sungay North, Sungay South, Iruhin West,
Iruhin South and Dapdap East in Tagaytay City.
Bgy. Casile in Cabuyao, Laguna

REASON: Insulator washing along Tagaytay – Calamba Road in Bgy.
Iruhin West, Tagaytay City, Cavite.

THURSDAY, MARCH 15, 2012
BATANGAS (STO. TOMAS)
BETWEEN 8:00AM AND 5:00PM – THW WHOLE OF CIRCUIT MAKBAN 56MB
St. Thomas Paper Corp. in Bgy. San Felix, Sto. Tomas.

REASON: Replacement of rotten poles, cross-arms and corroded
insulators along Makban – Calamba transmission lines by
NGCP personnel.

FRIDAY TO SATURDAY, MARCH 16 - 17, 2012
BULACAN (MEYCAUAYAN)
BETWEEN 11:00PM AND 11:30PM (FRI., 03/16/12) AND THEN BETWEEN 4:30AM
AND 5:00AM (SAT., 03/17/12) – PORTION OF CIRCUIT MEYCAUAYAN 42YM
Portion of Iba Road from North Luzon Expressway to and
including Sto. Niño Homes Phase II, Mt. Carmel Subd., Emco Subd., Ana
Maria Subd., Meridian Industrial Park and Sterling Industrial Park in
Bgys. Calvario, Pandayan, Iba and Pantoc.

BETWEEN 11:00PM (FRI., 03/16/12) AND 5:00AM (SAT., 03/17/12) –
PORTION OF CIRCUIT MEYCAUAYAN 42YM
The whole of Muralla Industrial Subd. in Bgy. Perez.

REASON: Various maintenance works at Muralla Industrial Subd. in
Bgy. Perez, Meycauayan, Bulacan.

SATURDAY, MARCH 17, 2012
MAKATI CITY
BETWEEN 9:00AM AND 3:00PM – PORTION OF CIRCUIT MALIBAY 51VJ
Portion of Binay St. corner Dallas St. including Globe Telecom
cabinet in Bgys. Pio Del Pilar and Bangkal.

REASON: Replacement of rotten poles and line maintenance works along
Binay St. in Bgy. Pio Del Pilar, Makati City.

SUNDAY, MARCH 18, 2012
BULACAN (MALOLOS CITY)
BETWEEN 3:00AM AND 9:00AM – PORTION OF CIRCUIT TABANG 35YH
Coca Cola – Malolos Sales Office, Cosmetique Asia Corp.,
Glowdell Lab, Liquid Packaging Corp., Prima Plastics Mfg., Purefeeds
and Reed Steel Fabricators in First Bulacan Industial City, Bgy.
Tikay.

REASON: Relocation of primary facilities affected by Government
project along McArthur Highway in Malolos City, Bulacan.




MERALCO exerts all efforts to restore electric service as scheduled.
However, there are instances when due to unavoidable circumstances,
restoration may extend beyond the published schedule.
For more information, please contact our CALL CENTER at telephone
nos. 16211 / 631-1111, fax nos. 1622-8554 / 1622-8556, or e-mail address
callcenter.tech.assist@meralco.com.ph. For faster resolution of inquiries,
please use the Bill ID Number or Service Identification Number (SIN)
indicated in your electric bills.
For those who prefer to receive this schedule via e-mail, simply
write to us at callcenter.tech.assist@meralco.com.ph and type in the phrase
"Request for weekly schedule".




VIEW YOUR BILL ON LINE. VISIT OUR WEBSITE!
www.meralco.com.ph



Privileged/Confidential information contained in this e-mail and its attachment/s is intended solely for the use of the addressee and is not meant for reproduction, disclosure and distribution to others without previous authorization from Meralco or its authorized representative. If erroneously sent or received, please do not open and delete the same from your system. Unless, otherwise specifically stated and confirmed by the authorized representative of Meralco, the opinions and views that may be contained therein are personal to the sender.

Monday, March 5, 2012

MERALCO Maintenance Schedule for March 5 - 11, 2012 (Sent by: Janice V. De Asis)

=======================================================================
WELCOME TO MERALCO'S MAINTENANCE SCHEDULE VIA E-MAIL
------------------------------------------------------------------------------------------------------------------

Attached is the schedule of our pre-arranged power interruptions for March
5 to 11, 2012. This serves as a general information guide and should not
be directly construed as an interruption advisory to the e-mail recipients.

Please call us at telephone numbers 16211 or 631-1111 for verification of
power interruption schedule.

If you wish to unsubscribe, please send us an e-mail and type in the word
"Unsubscribe".

Thank you very much.




MAINTENANCE SCHEDULE

To carry out necessary maintenance and upgrading works on various
MERALCO distribution facilities, electric service will be temporarily
interrupted on the following dates and places:


TUESDAY, MARCH 6, 2012
MANILA (BINONDO; SAN NICOLAS; AND TONDO)
BETWEEN 8:00AM AND 9:00AM AND THEN BETWEEN 2:00PM AND 3:00PM – THE
WHOLE OF CIRCUITS BINONDO 14N; AND PALOMAR 18L
Portion of Jose Abad Santos Ave. and Reina Regente St. from C.
La Torre St. to Plaza Lorenzo Ruiz including Felipe II, Lachambre,
Alvarado, Oriente, Insular and Nueva Sts.; San Lorenzo Ruiz Academy,
Yellow Cab Restaurant and Lucky Textile Bldg. in Tondo and Binondo.
Portion of Barraca, Urbiztondo and Elcano Sts. from Dasmariñas
to Lavezares Sts. including Jaboneros, San Nicolas and Ilang – Ilang
Sts.; National Mapping & Resource Information Authority, CISCO Bldg.,
Philippine National Bank and Ruby Ngo Bldg. in San Nicolas.

REASON: Preventive maintenance and testing works inside Meralco –
Palomar substation.

CAVITE (DASMARIÑAS CITY)
BETWEEN 9:00AM AND 1:00PM – PORTION OF CIRCUIT GMA 46XF
Portion of Paliparan III Road from Mabuhay City Mini-Market to
and including Mabuhay City I, II & II-E and IV in Bgy. Paliparan III.

REASON: Reconstruction of primary lines and replacement of rotten
cross-arms at Mabuhay City Mini-Market in Bgy. Paliparan
III, Dasmariñas City, Cavite.

TUESDAY TO WEDNESDAY, MARCH 6 - 7, 2012
MANILA; AND PASAY CITY
BETWEEN 11:30PM AND 11:45PM (TUE., 03/06/12) AND THEN BETWEEN 5:15AM
AND 5:30AM (WED., 03/07/12) – PORTION OF CIRCUIT MALATE 14J
Portion of Leon Guinto Sr., Pablo Ocampo Sr. (Vito Cruz) and
Sandejas Sts. from Dagonoy St. to 13 De Agosto St. including One
Oasis Place, College of Saint Benilde and portion of St.
Scholastica's College in Malate, Manila.
Portion of Taft Ave. Ext. from 13 De Agosto St. to Lukban St.
including Donada St.; San Isidro Catholic Church Compound, Jollibee –
Taft, G & B Bldg., Jeepney Shopping Center, Metrobank, Pasay Police
Substation and Wellton Bldg. in San Isidro and Sta. Clara, Pasay
City.
Portion of Donada St. from San Juan St. to Sen. Gil Puyat Ave.
(Buendia) including National Philippine Union Mission of Seventh –
Day Adventist Church and Manila Sanitarium and Hospital in San Isidro
and San Jose, Pasay City.
Portion of A. Luna St. from Sen. Gil Puyat Ave. (Buendia) to
Lukban St. including Cartimar Ave., Villaruel, Int. Luna, Dancel
Sts.; CPDC Training Center, Cartimar International Shopping Complex
and Philippine Chung Hua Academy in Sta. Clara, Pasay City.

BETWEEN 11:30PM AND 11:59PM (TUE., 03/06/12) AND THEN BETWEEN 5:00AM
AND 5:30AM (WED., 03/07/12) – PORTION OF CIRCUIT PACO 422VY
Portion of Sen. Gil Puyat Ave. (Buendia) from F. B. Harrison
St. to Taft Ave. Ext. including David and Leveriza Sts.; Mercury
Drug, Metrobank and EGI Rufino Plaza in San Jose, Pasay City.
Portion of F. B. Harrison St. from near Sen. Gil Puyat Ave.
(Buendia) to P. Manahan St. including Antipolo, San Luis, Santa
Escolastica, Roberts, M. Santos and Willams Sts.; U.S. Department of
Veterans Affairs, Almeda Bldg. – PEZA, OWWA Center, Department of
Foreign Affairs, Nolboo Restaurant, Poweree Bldg., Hanjin Office and
Maribella 1 Bldg. in San Jose, Pasay City.

BETWEEN 11:30PM (TUE., 03/06/12) AND 5:30AM (WED., 03/07/12) –
PORTION OF CIRCUITS PACO 422VY; AND MALATE 14J AND 19J
Portion of Villaruel St. from F. B. Harrison St. to near A.
Luna St. including Leveriza St.; Villaruel Tower, Blessed Elena
Academy and Victoria Court in Sta. Clara, Pasay City.
Portion of Leveriza St. from Sen. Gil Puyat Ave. (Buendia) St.
to Tupas St. including Villaruel, Mabolo, Propietarios, Doña Moneng,
Dancel, Rufino Mateo (Cinco De Junio), Col. Doro, P. Medina, 7th
Sts.; Aqualand Apartments, Cartimar Shopper's Arcade, Sunset View
Condominium, CTC Bldg., Pasay Volunteer's Fire Brigade, Eurobread
Bakery, Lianas Daily Mart & Department Store in Sta. Clara, Pasay
City.

REASON: 1. Replacement of rotten pole along Leveriza St. near
Villaruel St. in Sta. Clara, Pasay City.
2. Replacement of rotten pole along Leveriza St. near
Tupaz St. in Sta. Clara, Pasay City.

WEDNESDAY, MARCH 7, 2012
LAGUNA (CALAMBA)
BETWEEN 12:00NN AND 3:00PM – PORTION OF CIRCUIT CANLUBANG 52XE
Avida Village in Bgy. Canlubang.

REASON: Relocation of poles along Spine Road in Nuvali, Bgy.
Canlubang, Calamba, Laguna.

WEDNESDAY TO THURSDAY, MARCH 7 - 8, 2012
PASIG CITY (BAGONG ILOG)
BETWEEN 11:00PM AND 11:30PM (WED., 03/07/12) AND THEN BETWEEN 4:30AM
AND 5:00AM (THU., 03/08/12) – PORTION OF CIRCUIT HILLCREST 415VZ
Portion of Carlos P. Garcia Ave. (C-5 Road) from Canley Road
(Danny Floro) to Pasig Boulevard Ext. (C. Raymundo) including Sta.
Rosa De Lima St.; and Mary Immaculate Hospital.
Portion of Pasig Boulevard Ext. (C. Raymundo) from M. San
Buenaventura St. to A. Flores St. including Corporal Cruz St.; Atom
Chemical, Sta. Rosa De Lima Parochial School, IYS Building, Tropical
Hut and King Arthur's Lodge.

BETWEEN 11:00PM (WED., 03/07/12) AND 5:00AM (THU., 03/08/12) –
PORTION OF CIRCUIT HILLCREST 415VZ
Portion of P. Garcia Ave. (C-5 Road) from near Pasig Boulevard
Ext. (C. Raymundo) to and including Morning Star Milling, A. Flores,
Aplaya, Pvt. Aurellana, Dr. Maximo Flores, Francisco, Riverside, San
Roque, Santiago, Sgt. Limjoco, Sgt. Pascua, Sgt. R. Velasquez and B.
Tatco Sts.; Bio Pure, Metrolab Industries, Universal Robina – Flour
Mills, Universal Robina – Pasta Mfg., Universal Robina – Corn
Products, Tantoco Coal Mines Compound, Hercules Metal and Pittsburgh
Trade Center.

REASON: Replacement of rotten poles along Sgt. Pascua St. in Bgy.
Bagong Ilog, Pasig City.

THURSDAY TO FRIDAY, MARCH 8 – 9, 2012
LAGUNA (SAN PEDRO)
BETWEEN 11:00PM AND 11:30PM (THU., 03/08/12) AND THEN BETWEEN 4:30AM
AND 5:00AM (FRI., 03/08/12) – PORTION OF CIRCUITS SAN PEDRO 46WH AND
425WH
Portion of A. Mabini St. and San Pedro – Sta. Rosa National
Highway from Magsaysay Road to near Meralco – San Pedro Substation
including Camella Milan Subd., Camella Homes South Subd., Aurora
Heights Subd., Lakeville Subd., Elvinda Village, Sibulo II Subd.,
Villa Castillo Compound, Olivares Homes, Guevarra Subd., Comphil
Subd., Greatland Village, Cataquiz Subd. and St. Francis Homes 3
Subd. in Bgys. Nueva, San Antonio, San Vicente, Landayan, Sto. Niño,
San Roque and Cuyab.

BETWEEN 11:00PM (THU., 03/08/12) AND 5:00AM (FRI., 03/08/12) –
PORTION OF CIRCUIT SAN PEDRO 46WH
Portion of San Pedro – Sta. Rosa National Highway from Meralco
– San Pedro substation to near Severina Homes in Bgy. Nueva.

REASON: Relocation of primary facilities affected by DPWH road
widening project along San Pedro – Sta. Rosa National
Highway in Bgy. Nueva, San Pedro, Laguna.

FRIDAY, MARCH 9, 2012
QUEZON CITY
BETWEEN 8:00AM AND 9:00AM AND THEN BETWEEN 3:00PM AND 4:00PM – THE
WHOLE OF CIRCUITS LA LOMA 15VB AND 18VB
Portion of Banawe Ave. from Pagataan St. to N. S. Amoranto Sr.
Ave. including Palali, Sta. Catalina, Sgt. D. M. Alcaraz, Pao, Sicaba
and Sibuyan Sts. in Bgys. Manresa, Sienna and St. Peter.
Portion of D. Tuazon Ave. from N. S. Amoranto Sr. Ave. to Maria
Clara St. including Macopa, Don Manuel Agregado, Samat, Cordillera,
Calamba; McDonald's Restaurant and Red Ribbon Bakeshop in Bgys. St.
Peter and Lourdes.
Portion of Simoun St. from D. Tuazon Ave. to Mariveles St.
including portion of Kanlaon and Mayon Aves.; Speaker Perez, Apo, Ipo
and Cadig Sts. in Bgys. Lourdes and San Isidro Labrador.

REASON: Preventive maintenance and testing works inside Meralco –
La Loma substation.

SATURDAY, MARCH 10, 2012
CAVITE (IMUS)
BETWEEN 1:00AM AND 4:00AM – PORTION OF CIRCUIT IMUS 424WK
Portion of Gen. Yengco and Bisita Sts. from Villanueva Subd.,
Bgy. Medicion I-C to Tirona Highway including Plaridel Subd.,
Greentown II Subd., Velarde Village and Angel Village; Bgys. Medicion
I-A & I-C, Toclong II-A & II-B, Medicion II-A & II-B II-C in Imus;
Allenville Townhomes in Bgys. Balsahan – Bisita and Manggahan – Lawin
in Kawit.

REASON: Loadshifting of portion of 34.5kV circuit Imus 424WK to
Bacoor 412WX.




MERALCO exerts all efforts to restore electric service as scheduled.
However, there are instances when due to unavoidable circumstances,
restoration may extend beyond the published schedule.
For more information, please contact our CALL CENTER at telephone
nos. 16211 / 631-1111, fax nos. 1622-8554 / 1622-8556, or e-mail address
callcenter.tech.assist@meralco.com.ph. For faster resolution of inquiries,
please use the Bill ID Number or Service Identification Number (SIN)
indicated in your electric bills.
For those who prefer to receive this schedule via e-mail, simply
write to us at callcenter.tech.assist@meralco.com.ph and type in the phrase
"Request for weekly schedule".




VIEW YOUR BILL ON LINE. VISIT OUR WEBSITE!
www.meralco.com.ph



Privileged/Confidential information contained in this e-mail and its attachment/s is intended solely for the use of the addressee and is not meant for reproduction, disclosure and distribution to others without previous authorization from Meralco or its authorized representative. If erroneously sent or received, please do not open and delete the same from your system. Unless, otherwise specifically stated and confirmed by the authorized representative of Meralco, the opinions and views that may be contained therein are personal to the sender.