Friday, March 28, 2014

MERALCO Maintenance Schedule for March 31 to April 6, 2014 (Grp2) (Sent by: Janice V. De Asis)

=======================================================================
WELCOME TO MERALCO'S MAINTENANCE SCHEDULE VIA E-MAIL
------------------------------------------------------------------------------------------------------------------

Attached is the schedule of our pre-arranged power interruptions for March 31 to April 6, 2014.  This serves as a general information guide and should not be directly construed as an interruption advisory to the e-mail recipients.

Please call us at telephone numbers 16211 or 631-1111 for verification of power interruption schedule.

If you wish to unsubscribe, please send us an e-mail and type in the word "Unsubscribe".

Thank you very much.



MAINTENANCE SCHEDULE

To carry out necessary maintenance and upgrading works on various MERALCO distribution facilities, electric service will be temporarily interrupted on the following dates and places:


TUESDAY, APRIL 1, 2014
RIZAL PROVINCE (TAYTAY)
    BETWEEN 12:01AM AND 5:00AM – PORTION OF CIRCUIT DOLORES 44XM
    Portion of Manila East Road from near Rizal St. to and including Metrobank in Bgy. San Juan.

    REASON: Relocation of pole affected by DPWH road widening project along Manila East Road in Bgy. San Juan, Taytay, Rizal.
MAKATI CITY (RIZAL); AND TAGUIG CITY (USUSAN)
    BETWEEN 12:30AM AND 1:00AM AND THEN BETWEEN 5:00AM AND 5:30AM – PORTION OF CIRCUIT MALIBAY 412VJ
    Portion of Carlos P. Garcia Ave. (C-5 Road) from Woodpecker St. to near Upper McKinley Road including Blue Bird, Bluevos, Oriole, Milkweed, Aguila, Maya, Blue Berry and Rose Sts. in Bgy. Rizal, Makati City.

    BETWEEN 12:30AM AND 5:30AM – PORTION OF CIRCUIT MALIBAY 412VJ
    Portion of Carlos P. Garcia Ave. (C-5 Road) from Upper McKinley Road to and including SM Aura Premier, Ridgewood Towers, Ridgewood Square, Jollibee, Shakey's Restaurant and Shell Gas station in Bgy. Ususan, Taguig City.

    REASON: Line reconductoring works along Carlos P. Garcia Ave. (C-5 Road) in Bgy. Ususan, Taguig City.
BULACAN (BOCAUE)
    BETWEEN 9:00AM AND 3:00PM – PORTION OF CIRCUIT SAOG 412SAO
    Portion of MacArthur Highway from near Bocaue Bridge to Centro 1st St. including Biñang 1st Road; Biñang 1st Barangay Hall and Excel Wood Industries in Bgys. Biñang 1st and Bunlo.

    REASON: Relocation of facilities affected by DPWH Bunlo Bridge reconstruction and widening project along MacArthur Highway in Bgy. Bunlo, Bocaue, Bulacan.
TUESDAY TO WEDNESDAY, APRIL 1 – 2, 2014
BULACAN (SAN JOSE DEL MONTE CITY); AND CALOOCAN CITY (NORTH)
    BETWEEN 11:00PM AND 11:30PM (TUE., 04/01/14) AND THEN BETWEEN 4:30AM AND 5:00AM (WED., 04/02/14) – PORTIONS OF CIRCUITS CAMARIN 432TC AND 433TC
    Portion of Old Zabarte Road from Celina Homes Subd. to near Langit Road including Goldhill Place Subd., La Forteza Subd. and PHHC Camarin Subd. (Area A) in Bgy. Camarin, Caloocan City.
    Portion of Langit Road from near Old Zabarte Road to and including Modern Living Subd., Brixtonville Subd., Shelterville 1 Subd., Phase 4 Packages 1-9 Subds., Phase 9  Packages 2-9 Subds. and Phase 10 Packages 1-6 Subds. in Bgys. Bagong Silang – Kaliwa, Bagumbong and Camarin in Caloocan City.
    Portion of Kaagapay St. from Katarungan St. to Malaria Road including NHC Tala Estate Subd., LD-NHA Housing Project Subd., Tala – Medium Rise Housing (MRH) Project Subd., Phase 12 Packages 1-3 Subds.; NHC Road; and Victoria Wave Limited Knitting Mill in Bgy. Tala, Caloocan City.

    BETWEEN 11:00PM (TUE., 04/01/14) AND 5:00AM (WED., 04/02/14) – PORTION OF CIRCUITS CAMARIN 432TC AND 433TC
    Portion of Old Zabarte Road from PNP Bagong Silang Substation 3 Office to Langit Road including Phase 3 Packages 1-3, Phase 5A Packages 1-4 Subds.; Bicol Apparel Steam Laundry and Bagong Silang Barangay Hall in Bgys. Bagong Silang – Kanan and Camarin, Caloocan City.
    Portion of Langit Road from Old Zabarte Road in Bgy. Bagong Silang – Kanan, Caloocan City to Dela Costa Homes IV in Bgy. Graceville, San Jose Del Monte City, Bulacan; Phase 1 Packages 1-4 Subds., Phase 2 Packages 1-3 Subds., Phase 7 Packages 1-11 Subds., Phase 8 Packages 1-14 Subds.; Simplicity Go-Szap Supermarket, NHA Office and Mercury Drug Store in Bgy. Bagong Silang – Kanan, Caloocan City; and Evergreen Heights Subd. Phase 1 in Bgy. Gaya – Gaya, San Jose Del Monte City, Bulacan.

    REASON: Installation of additional lightning protection devices along Old Zabarte and Langit Roads in Bgy. Bagong Silang - Kanan, Caloocan City.
WEDNESDAY TO THURSDAY, APRIL 2 - 3, 2014
LAGUNA (CALAMBA)
    BETWEEN 11:00PM (WED., 04/02/14) AND 4:00AM (THU., 04/03/14) – PORTION OF CIRCUIT CANLUBANG 47XE
    Portion of Calamba - Real National Highway from Calamba Crossing to and including Manoto-Malihan Subd., Rizal Park Subd., F. Cuervo Subd., El Real Cpd. and ATDRMAN II Village; Mercury Drug Store, BPI, Philippine Veterans Bank, Chowking Restaurant, Calamba Ice Plant, Waltermart, Gruppo Medica Inc. and Calamba Water District in Bgy. Real.
    Portion of San Vicente Ferrer St. and Bacnotan Drive from PNR Road to and including Dept. of Education Bldg., IPF-TAK Inc., Calamba City Hall, NALCO Phil. Inc., Bacnotan Steel Corp., NYK Auto Logistics Phil. and Royal Garden Spa; St. Vincent Village, Casa Roma Subd., Villa de Calamba, Maria Makiling Heights and La Mesa Ridge Subd. in Bgys. Real, La Mesa and Town Proper.  

    REASON: Various maintenance works along Calamba - Real National Highway and San Vicente Ferrer St. in Bgy. Real, Calamba, Laguna.

SATURDAY, APRIL 5, 2014
MANILA (SAMPALOC); AND QUEZON CITY
    BETWEEN 9:00AM AND 9:15AM AND THEN BETWEEN 2:30PM AND 2:45PM – THE WHOLE OF CIRCUIT STA. MESA 18F
    Portion of Visayan St. from Meralco – Sampaloc substation to Batanes St. including 4 de Julio St. in Bgy. San Isidro, Quezon City.
    Portion of G. Tuazon St. from Blumentritt St. to Prudencio St. including Algeciras, Samar, T. Pinpin and Valdez Sts. in Sampaloc, Manila.

    BETWEEN 9:00AM AND 9:30AM AND THEN BETWEEN 2:30PM AND 3:00PM – PORTION OF CIRCUIT STA. MESA 19F
    Portion of D. Santiago St. from Visayan Ave. to Luzon Ave. including Palaez Elementary School in Sampaloc, Manila.

    BETWEEN 9:00AM AND 3:00PM – PORTION OF CIRCUITS PANDACAN 18M; AND STA. MESA 19F
    Portion of Buenos Aires St. from Altura St. to D. Santiago St.; portion of Mindanao Ave. from Cebu St. to D. Santiago St. including Palawan and West Vigan Sts. in Sampaloc, Manila.

    REASON: Line maintenance works along D. Santiago St. in Sampaloc, Manila.

SUNDAY, APRIL 6, 2014
LAGUNA (SAN PABLO CITY)
    BETWEEN 7:30AM AND 12:30PM – PORTION OF CIRCUIT SAN PABLO 45WJ
    Portion of PNR Railroad Track from San Francisco Subd. to San Joaquin Barangay Road in Bgys. San Francisco, San Gregorio, San Joaquin, Santisino Rosario, Soledad and Sta. Maria.

    REASON: Replacement of rotten poles and cross-arms along PNR Railroad Track in Bgy. San Francisco, San Pablo City, Laguna.

    MERALCO exerts all efforts to restore electric service as scheduled. However, there are instances when due to unavoidable circumstances, restoration may extend beyond the published schedule.
    For more information, please contact our CALL CENTER at telephone no. 16211 / 631-1111, fax no. 1622-8554 / 632-8554, or e-mail address callcenter.tech.assist@meralco.com.ph. For faster resolution of inquiries, please use the Bill ID Number or Service Identification Number (SIN) indicated in your electric bills.
    For those who prefer to receive this schedule via e-mail, simply write to us at callcenter.tech.assist@meralco.com.ph and type in the phrase "Request for weekly schedule".



    VIEW YOUR BILL ON LINE. VISIT OUR WEBSITE!
    www.meralco.com.ph



    Privileged/Confidential information contained in this e-mail and its attachment/s is intended solely for the use of the addressee and is not meant for reproduction, disclosure and distribution to others without previous authorization from Meralco or its authorized representative.  If erroneously sent or received, please do not open and delete the same from your system.  Unless, otherwise specifically stated and confirmed by the authorized representative of Meralco, the opinions and views that may be contained therein are personal to the sender.