Monday, July 28, 2014

MERALCO Maintenance Schedule for July 28 - August 3, 2014 (Grp2) (Sent by: Janice V. De Asis)

=======================================================================
WELCOME TO MERALCO'S MAINTENANCE SCHEDULE VIA E-MAIL
------------------------------------------------------------------------------------------------------------------

Attached is the schedule of our pre-arranged power interruptions for July 28 to August 3, 2014.  This serves as a general information guide and should not be directly construed as an interruption advisory to the e-mail recipients.

Please call us at telephone numbers 16211 or 631-1111 for verification of power interruption schedule.

If you wish to unsubscribe, please send us an e-mail and type in the word "Unsubscribe".

Thank you very much.



MAINTENANCE SCHEDULE

To carry out necessary maintenance and upgrading works on various MERALCO distribution facilities, electric service will be temporarily interrupted on the following dates and places:


MONDAY, JULY 28, 2014
PASIG CITY (UGONG)
    BETWEEN 9:30AM AND 2:30PM – PORTION OF CIRCUIT SM SHANGRI-LA 45VR
    Portion of Valle Verde 3 Subd. including Acacia, Dao, Guijo, Ipil, Malipajo, Molave and Narra Sts.

    REASON:  Line maintenance works along Molave and Malipajo Sts. in Valle Verde 3, Bgy. Ugong, Pasig City.

MONDAY TO TUESDAY, JULY 28 - 29, 2014
PASIG CITY
    BETWEEN 11:30PM AND 11:59PM (MON., 07/28/14) AND THEN BETWEEN 4:00AM AND 4:30AM (TUE., 07/29/14) – PORTION OF CIRCUIT PASIG 43ZK
    Portion of Caruncho and Urbano Velasco Aves. from Market Ave. to and including Ferrer Cpd., Jabson Cpd., Villa Antonio Cpd. and Garden Royale Villas; R. Cruz, Farmers, A. Esguerra, Acacia and Venancio Caliwag Sts.; New Pasig Public Market, Pasig Supermarket and Jollibee Restaurant in Bgys. Bambang, Malinao, Pinagbuhatan and San Nicolas.

    BETWEEN 11:30PM (MON., 07/28/14) AND 4:30AM (TUE., 07/29/14) – PORTION OF CIRCUIT PASIG 43ZK
    Portion of San Agustin Ave. from Carauncho Ave. to and including Asahi Electrical, Jaynith's Supermarket, Lianas Supermarket and D. R. Zaragoza Machine Shop; Market Ave., Francisco Soriano, Victoriano Baltazar, Bolante and Elpidio Santos Sts. in Bgys. Pinagbuhatan, San Nicolas, Palatiw and Sumilang.

    REASON:  Line maintenance works along San Agustin Ave. in Bgy. Pinagbuhatan, Pasig City.

WEDNESDAY, JULY 30, 2014
MANILA (INTRAMUROS; AND PORT AREA)
    BETWEEN 8:00AM AND 8:30AM AND THEN BETWEEN 12:30PM AND 1:00PM – PORTION OF CIRCUIT BINONDO 41N
    Portion of Rail Road Drive from 16th St. to 11th St. including in Port Area.
    Portion Bonifacio Drive from 11th St. to 2nd St. including DPWH Kawilihan Bldg., Asian Terminal Inc. Compound, Bureau of Lands, Manila Times, Great Domestic Insurance Company of the Philippines, Eastern Shipping Lines, Daily Express, Order of the Knight of Rizal, Club Intramuros and Philippine National Red Cross in Intramuros and Port Area.
    Portion of 2nd St. from Bonifacio Drive to and including Gawad Kalinga Village (BASECO), Bagong Lupa Village (BASECO), Prudential Villages 1 – 2; AG & P Compound, Philippine Postal Corp., DPWH Focus Bldg., Movers & Managers Corp., Northstar Transport, BASECO Shipyard Corp., Tacoma Integrated Port Services and Pioneer Logistics & Rental Corp. in Port Area.

    BETWEEN 8:00AM AND 1:00PM – PORTION OF CIRCUIT BINONDO 41N
    Portion of Roxas Boulevard from 16th St. to Anda Circle in Port Area.

    REASON:    Replacement of hazardous cracked pole along Roxas Blvd. corner 16th St. in Port Area, Manila.

MALABON CITY
    BETWEEN 9:00AM AND 3:00PM – PORTION OF CIRCUIT MALABON 43YD
    Portion of Rizal Blvd. Ext. and Mayor Paterio Aquino Ave. (Letre Road) from Philippine Business Bank to Our Lady of Lourdes Eternal Park including Rufina Patis Factory, BDO and Infinity Plastic Packaging; Magsaysay, Villanueva and Mesina Sts. in Bgys. San Agustin and Tonsuya.
    Along Gen. P. Borromeo St. from Mayor Paterio Aquino Ave. (Letre Road) to Alupihang Dagat St. in Bgys. Longos

    REASON:   Relocation of primary facilities affected by DPWH reconstruction of Malabon bridge along Rizal Ave. Ext., Bgy. Tonsuya, Malabon City

WEDNESDAY TO THURSDAY, JULY 30 - 31, 2014
**MANDALUYONG CITY; AND PASIG CITY
    BETWEEN 11:30PM AND 11:59PM (WED., 07/30/14) AND THEN BETWEEN 4:00AM AND 4:30AM (THU., 07/31/14) – PORTION OF CIRCUIT SM SHANGRI-LA 52VR
    Portion of Pearl Drive from Pearl Plaza to and including Manila Luxury Condominium and Philippine Coconut Research Development Foundation Compound in Ortigas Commercial Center, Bgy. San Antonio, Pasig City.

    BETWEEN 11:30PM (WED., 07/30/14) AND 4:30AM (THU., 07/31/14) – PORTION OF CIRCUIT SM SHANGRI-LA 52VR
    Portion of Lourdes St. from St. Francis St. to Pearl Drive including San Miguel Properties Center Bldg. and Sonata Residences in Bgy. Wack Wack Greenhills East, Mandaluyong City; Richmond Hotel, Medico Bldg. and Greenrich Mansions in Ortigas Commercial Center, Bgy. San Antonio, Pasig City.

    REASON:     Line reconstruction works along Lourdes St. in Ortigas Commercial Center, Bgy. San Antonio, Pasig City.

SUNDAY, AUGUST 3, 2014
BULACAN (MALOLOS)
    BETWEEN 1:00AM AND 4:00AM – PORTION OF CIRCUITS TABANG 33YH AND 35YH
    Portion of Calle Hagonoy from Purok 5 in Bgy. San Pablo to and including Purok 5 in Bgy. Santor.
    Coca Cola – Malolos Sales Office, Cosmetique Asia Corp., Glowdell Lab, Liquid Packaging Corp., Prima Plastics Mfg., Purefeeds, Sucere Foods and Reed Steel Fabricators in First Bulacan Industial City, Bgy. Tikay.
    Portion of Estrella St. from near Deogracias Subd. to and including Bgys. Mambog, Babatnin, Bagna, Balayong, Bangkal, Caliligawan, Masile, Matimbo, Namayan, Niugan, Pamarawan, Panasahan and Taal.

    REASON:  Various maintenance works inside Meralco – Tabang substation.
*QUEZON CITY (NEW MANILA)
    BETWEEN 12:01AM AND 12:30AM AND THEN BETWEEN 4:30AM AND 5:00AM – PORTION OF CIRCUIT KAMUNING 425VP
    Portion of E. Rodriguez Ave. from Campanilla St. to Doña Hemady St. including Mabolo, 12th and Alabama Sts.; Petron Gas Station, Tri - Place Hotel and Happy Sauna in Bgy. Kristong Hari.
    Portion of Doña M. Hemady St. from E. Rodriguez Ave. to and including Woodside Homes in Bgy. Kristong Hari.
    BETWEEN 12:01AM AND AND 5:00AM – PORTION OF CIRCUITS KAMUNING 425VP; AND QUEZON CITY 14VA
    Portion of E. Rodriguez Ave. from Christ the King Church and Seminary to and including Trinity College of Quezon City, St. Luke's Hospital, St. Joseph's College, Pizza Hut, Caltex Gas Station, Metro Supermart, Mercury Drug Store, Quezon City Sports Club and PETA Theater; Sta. Ignaciana, 16th, 17th, 18th and 19th Sts. in Bgy. Kalusugan; in Bgy. Damayan Lagi.
    Portion of Gilmore Ave. from E. Rodriguez Ave. to and including 10th, 11th and 13th Sts.; and Daughters of St. Mary of Leuca in Bgy. Damayan Lagi.
      REASON:     Line reconstruction works along E. Rodriguez Sr. Ave. in New Manila, Quezon City.


MERALCO exerts all efforts to restore electric service as scheduled. However, there are instances when due to unavoidable circumstances, restoration may extend beyond the published schedule.
For more information, please contact our CALL CENTER at telephone no. 16211 / 631-1111, fax no. 1622-8554 / 632-8554, or e-mail address callcenter.tech.assist@meralco.com.ph. For faster resolution of inquiries, please use the Bill ID Number or Service Identification Number (SIN) indicated in your electric bills.
For those who prefer to receive this schedule via e-mail, simply write to us at callcenter.tech.assist@meralco.com.ph and type in the phrase "Request for weekly schedule".



VIEW YOUR BILL ON LINE. VISIT OUR WEBSITE!
www.meralco.com.ph



*Additional PPI

**Revised PPI (changes already incorporated)

Privileged/Confidential information contained in this e-mail and its attachment/s is intended solely for the use of the addressee and is not meant for reproduction, disclosure and distribution to others without previous authorization from Meralco or its authorized representative.  If erroneously sent or received, please do not open and delete the same from your system.  Unless, otherwise specifically stated and confirmed by the authorized representative of Meralco, the opinions and views that may be contained therein are personal to the sender.

Thursday, July 24, 2014

MERALCO Maintenance Schedule for July 21 - 27, 2014 (Grp2) (Sent by: Janice V. De Asis)

=======================================================================
WELCOME TO MERALCO'S MAINTENANCE SCHEDULE VIA E-MAIL
------------------------------------------------------------------------------------------------------------------

Attached is the schedule of our pre-arranged power interruptions for July 21 to 27, 2014.  This serves as a general information guide and should not be directly construed as an interruption advisory to the e-mail recipients.

Please call us at telephone numbers 16211 or 631-1111 for verification of power interruption schedule.

If you wish to unsubscribe, please send us an e-mail and type in the word "Unsubscribe".

Thank you very much.



MAINTENANCE SCHEDULE

To carry out necessary maintenance and upgrading works on various MERALCO distribution facilities, electric service will be temporarily interrupted on the following dates and places:


THURSDAY TO FRIDAY, JULY 24 – 25, 2014
PASIG CITY (BAGONG ILOG)
    BETWEEN 11:00PM (THU., 07/24/14) AND 6:00AM (FRI., 07/25/14) – THE WHOLE OF CIRCUIT HILLCREST 423VZ  
         Along Cpl. Cruz and A. Flores St. from Eulogio Rodriguez Jr. Ave. (C-5 Road) to Pasig Blvd. Ext. including M. San Buenaventura and Sta. Rosa De Lima Sts.; Pasig View Lodge, King Arthur's Lodge, Atom Marketing, Cement Manufacturer's Asso. Of the Phils. and Sta. Rosa De Lima Parish Church.

    REASON:     Preventive maintenance and testing works inside Meralco – Hillcrest substation.


MERALCO exerts all efforts to restore electric service as scheduled. However, there are instances when due to unavoidable circumstances, restoration may extend beyond the published schedule.
For more information, please contact our CALL CENTER at telephone no. 16211 / 631-1111, fax no. 1622-8554 / 632-8554, or e-mail address callcenter.tech.assist@meralco.com.ph. For faster resolution of inquiries, please use the Bill ID Number or Service Identification Number (SIN) indicated in your electric bills.
For those who prefer to receive this schedule via e-mail, simply write to us at callcenter.tech.assist@meralco.com.ph and type in the phrase "Request for weekly schedule".



VIEW YOUR BILL ON LINE. VISIT OUR WEBSITE!
www.meralco.com.ph




Privileged/Confidential information contained in this e-mail and its attachment/s is intended solely for the use of the addressee and is not meant for reproduction, disclosure and distribution to others without previous authorization from Meralco or its authorized representative.  If erroneously sent or received, please do not open and delete the same from your system.  Unless, otherwise specifically stated and confirmed by the authorized representative of Meralco, the opinions and views that may be contained therein are personal to the sender.

Monday, July 14, 2014

MERALCO Maintenance Schedule for July 14 - 20, 2014 (Grp2) (Sent by: Janice V. De Asis)

=======================================================================
WELCOME TO MERALCO'S MAINTENANCE SCHEDULE VIA E-MAIL
------------------------------------------------------------------------------------------------------------------

Attached is the schedule of our pre-arranged power interruptions for July 14 to 20, 2014.  This serves as a general information guide and should not be directly construed as an interruption advisory to the e-mail recipients.

Please call us at telephone numbers 16211 or 631-1111 for verification of power interruption schedule.

If you wish to unsubscribe, please send us an e-mail and type in the word "Unsubscribe".

Thank you very much.



MAINTENANCE SCHEDULE

To carry out necessary maintenance and upgrading works on various MERALCO distribution facilities, electric service will be temporarily interrupted on the following dates and places:


TUESDAY, JULY 15, 2014
CAVITE (ALFONSO; AND TAGAYTAY CITY)
    BETWEEN 9:00AM AND 2:00PM – PORTION OF CIRCUIT TAGAYTAY WEST 312TGW
    Portion of Tagaytay – Alfonso National Highway from Western Union Residence Inn to Alfonso – Nasugbu Municipal boundary including Tagaytay Country Homes II Subd.; Bgys. Neogan, Mendez Crossing East, Bagong Tubig, Asisan and Zambal in Tagaytay City; Royal Tagaytay Estates Subd., Buck Estate, La Prairie Subd., Garden Hills Subd., Valley Farm Subd. and Scottsdale Classic Country Homes Subd.; Bgys. Amuyong, Bilog, Buck Estate, Kaysuyo, Kaytitinga I – III, Luksuhin Ibaba, Luksuhin Ilaya, Palumlum, Sikat, Sinaliw Munti and Upli in Alfonso.

    REASON:   Replacement of rotten crossarms and various maintenance works along Tagaytay – Alfonso National Highway in Bgy.  Neogan, Tagaytay City, Cavite.

TUESDAY TO WEDNESDAY, JULY 15 – 16, 2014
MAKATI CITY
    BETWEEN 11:30PM AND 11:59PM (TUE., 07/15/14) AND THEN BETWEEN 4:00AM AND 4:30AM (WED., 07/16/14) – PORTION OF CIRCUIT URDANETA 43VS  
         Hotel Céleste, AIM Conference Center and New World Hotel along Antonio Arnaiz Ave. (Pasay Road) in Bgy. San Lorenzo.
         Portion of Ayala Ave. from Bankers Centre Bldg. to and including Allied Bank Bldg., National Life Insurance Bldg., SGV I Bldg., SGV II Bldg., Bankmer Bldg. and one feed of PLDT Main Bldg. in Legaspi Village.  

    BETWEEN 11:30PM (TUE., 07/15/14) AND 4:30AM (WED., 07/16/14) – PORTION OF CIRCUIT URDANETA 43VS  
         Portion of Paseo de Roxas from Antonio Arnaiz Ave. (Pasay Road) to Dela Rosa St. including Legaspi St.; Asian Institute of Management, Greenbelt Mall Arcade, The Greenbelt Mall and Greenbelt – 5 in Legaspi Village, Bgy. San Lorenzo.

    REASON:    Commissioning of new 34.5kV electric circuit Legaspi 432RA in Legaspi Village, Makati City.

FRIDAY TO SATURDAY, JULY 18 - 19, 2014
**CAVITE (BACOOR)
    BETWEEN 11:00PM (FRI., 07/18/14) AND 4:00AM (SAT., 07/19/14) – PORTION OF CIRCUITS IMUS 422WK AND 423WK
    Portion of Molino Road from near Avenida Rizal ST. to and including Camella Springville West Phases 1, 2, 3, Camella Springville Central Phases 1, 2, 3 & 4, Camella Springville East Phases 1 & 2, Camella Springville South Phase 1, Camella Cerritos, Macaria Homes Phase 1 and Ponticelli Subd.; Perpetual Help College of Rizal and Supermart in Bgy. Molino II and III.
    Portion of Daang Hari Road from Sea Oil Gas Station to and including Cuevasville Subd., Camella Springville South Phase 2, Camella Springville Executive Subd. Phases II, Camella Springville Meadows, Lessandra Executive Village and Cerritos Heights in Bgys. Molino III and IV.

    REASON: Relocation of facilities affected by DPWH road widening project along Molino Road in front of Camella Springville Subd. in Bgy. Molino III, Bacoor, Cavite.

SUNDAY, JULY 20, 2014
CAVITE (GMA); AND LAGUNA (SAN PEDRO)
    BETWEEN 12:01AM AND 5:00AM – PORTION OF CIRCUITS GMA 41XF, 43XF AND 45XF
    Portion of Congressional Road from Altierra Subd. to near Mormon Church including Casa De Monteverde Subd. in Bgys. Francisco Reyes, Tiniente Tiago and Gregoria De Jesus, GMA, Cavite.
    Portion of Ramon Magsaysay Ave. from St. Joseph Ridgeview Subd. to near Reyvil Compound including St. Joseph Village 9 & 10, Villa Rosa Subd., Colina Subd., Filinvest Southern Heights II Subd., Villa San Pedro and Villa Consolacion in Bgys. Langgam, Estrella, Bagong Silang and Magsaysay, San Pedro, Laguna.

    REASON:     Replacement of rotten cross-arms and insulators along Congressional Road in Bgy. Gregoria De Jesus, GMA, Cavite.

BATANGAS PROVINCE (BATANGAS CITY; AND SAN PASCUAL)
    BETWEEN 1:00AM AND 5:00PM – THE WHOLE OF CIRCUITS NGCP - BATANGAS – BOLBOC 58BS; NGCP - BOLBOC 33ZZ AND 32ZZ; AND MAHABANG PARANG 32WZ
    Cocochem Agro-Industrial Park in Bgy. San Pascual, San Pascual.
    Bgys. Soro-soro Karsada, Bukal, Concepcion and Mahabang Parang in Batangas City.

    REASON:     NGCP Job:
      1. Replacement of rotten pole & cross-arms along Batangas City National Road in Batangas City.
       Meralco Job:
        2. To provide safe clearance during the erection of self support steel pole and conductor stringing along Diversion Road and National Road, Batangas City.
        3. Maintenance works inside NGCP Bolboc substation.

MANILA (ERMITA, MALATE AND PACO)
    BETWEEN 7:30AM AND 7:45AM AND THEN BETWEEN 1:15PM AND 1:30PM – PORTION OF CIRCUIT TEGEN 45B
    Portion of Zobel St. from Romualdez St. to San Marcelino including Teresa St. in Ermita.
    BETWEEN 7:30AM AND 8:00AM AND THEN BETWEEN 1:00PM AND 1:30PM – PORTION OF CIRCUIT TEGEN 45B
    Portion of Gen. Luna St. from near Padre Faura St. to Escoda St. including Swiss Inn and The Garden Plaza Bldg. 1 & 2, in Paco.
    Portion of F. T. Benitez St. from Escoda St. to near J. Nakpil St. including San Marcelino, Gen. Malvar and Modesto Sts.; DY International Bdlg. and New Gold Bond Marketing in Ermita and Malate.

    BETWEEN 7:30AM AND 1:30PM – PORTION OF CIRCUITS TEGEN 45B; AND TEGEN 46B – ERMITA 43S
    Portion of United Nations Ave. from Romualdez St. to near Taft Ave. including Tabacalera Cigars Bldg., Balite Flood Gate, Puregold Head Office, Philtrus Bank Insurance Commission of the Philippines, Lacson Commercial, Loadstar Shipping Company, Manila Teacher's Savings and Loan Association (MTSLAI), Philippine Bible Society, Simon Enterprises, Philippine President Lines, Philippine President Lines, Emilio Aguinaldo College, YIC Bdlg. and Western Police District in Ermita and Paco.
    Portion of San Marcelino St. from Zobel St. to Padre Faura St. including The Area President of the Church of Jesus Christ of Latter Day Saints, Jinss Lee Printing, Emilio Aguinaldo High School, Adamson University – Cardinal Santos Bldg. and Technological University of the Philippines (TUP) in Ermita.

    REASON:    Replacement of rotten poles along U.N. Avenue in Ermita and Paco, Manila.
QUEZON PROVINCE (LUCENA CITY; PAGBILAO; AND TAYABAS)
    BETWEEN 9:00AM AND 5:00PM – THE WHOLE OF CIRCUITS TAYABAS 44ZY AND 51ZY; AND PORTION OF CIRCUIT TAYABAS 48ZY
    Portion of Lucban – Tayabas National Road and Quezon Ave. from Lucban – Tayabas municipal boundary in Bgy. Dapdap, Tayabas to L. F. Teachers Village in Bgy. Cotta, Lucena City including Sitio Don Elpidio, Dela Torre Subd.,  Roma Rosa Subd., Doña Carmen Subd., Green Valley Subd., Sitio Isla Verde, Sitio Luad Loob, Tuazon Subd., St. Jude Village, Lita Subd. Phases 1 & 2, Angeles Zone Subd. I, II & III, Carmenville Subd., Lovely Meadows Subd., Lovely Village, Sumilang Subd. and Laval Subd. in Bgys. Camaysa, Dapdap, Ibas, Lalo, Matuena, Opias, Lita, Tongko, Wakas, Pandakaki, Mayowe, town proper in Tayabas, Quezon; Andaman Village, Capistrano Subd., De Mesa Cpd., Hermana Capistrano Subd. I & II, Pilar Cpd., Rey-Mar Cpd., Ridgewood Park Subd., San Isidro Subd., St. Micheal Subd., St. Peter Subd. II, Lopez Subd., Capitol Homes Subd., San Fernando Cpd., Zoleta Cpd., A. Orgas Subd., Campo Subd., Employees Village, Josephine Subd., L.I.C. Cpd., Marilag Village, North Employees Village, Pag-ibig Park Subd., Regis Cpd., Zaballero Subd., Marktown Subd., La Milagrosa Subd., Mt. Carmel Subd. and Sabina Subd. in Bgy. Cotta, Gulang – Gulang, babang Dupay, Ilayam and city proper in Lucena City.
    Along Padre Gomez St. and Pagbilao – Lucena Road from Quezon Ave. in Lucena city proper, Lucena, Quezon to and including the whole of Pagbilao; San Rafael Ville Subd., Santa Teresa Subd., Alpsville Subd., Cleade Heights Subd., Family Land Subd., Lucena Green Meadows Subd., R.J. Ville Subd., Riverside Subd., San Francisco Village, Villa Consuelo Subd., Villa Juliana Subd., Villa San Lorenzo Subd., VSJ East Subd., Bestland Homes Subd., Bliss Subd., Hills View Solcom Ville, Calmar Homes Subd., Executive Ville, Maryville Homes Subd., St. Thomas Village and Marville Subd. in Bgys. Barra, Dalahican, Ibabang Dupay, Mayao Castillo, Mayao Crossing, Mayao Kanluran, Mayao Parada, Mayao Silangan, Talao – Talao and city proper in Lucena City.
    Portion of Lucena Diversion Road from Palm Springs Subd. to Pagbilao - Lucena Road including Good Luck Subd., Happy Family Subd., Villa Aurea Subd., University Village, Grand Alliance Subd. and Metropolis Lucena Subd. in Bgys. Bocohan, Domoit, Ibabang Dupay, Ilayang Dupay, Mayao Kanluran & Silangan, Gulang – Gulang and city proper in Lucena City.

    REASON:   1.   Relocation of facilities along Tayabas – Lucban National Road affected by DPWH road widening project in Bgy. Camaysa, Tayabas, Quezon.
               2.   Relocation of facilities along Maharlika Highway affected by DPWH road widening project in Bgy. Ibabang Dupay, Lucena City, Quezon.
      3.   Preventive maintenance and testing works inside Meralco - Tayabas substation.
    MERALCO exerts all efforts to restore electric service as scheduled. However, there are instances when due to unavoidable circumstances, restoration may extend beyond the published schedule.
    For more information, please contact our CALL CENTER at telephone no. 16211 / 631-1111, fax no. 1622-8554 / 632-8554, or e-mail address callcenter.tech.assist@meralco.com.ph. For faster resolution of inquiries, please use the Bill ID Number or Service Identification Number (SIN) indicated in your electric bills.
    For those who prefer to receive this schedule via e-mail, simply write to us at callcenter.tech.assist@meralco.com.ph and type in the phrase "Request for weekly schedule".



    VIEW YOUR BILL ON LINE. VISIT OUR WEBSITE!
    www.meralco.com.ph



    **Revised PPI (changes already incorporated)

    Privileged/Confidential information contained in this e-mail and its attachment/s is intended solely for the use of the addressee and is not meant for reproduction, disclosure and distribution to others without previous authorization from Meralco or its authorized representative.  If erroneously sent or received, please do not open and delete the same from your system.  Unless, otherwise specifically stated and confirmed by the authorized representative of Meralco, the opinions and views that may be contained therein are personal to the sender.

    Monday, July 7, 2014

    MERALCO Maintenance Schedule for July 7 - 13, 2014 (Grp2) (Sent by: Janice V. De Asis)

    =======================================================================
    WELCOME TO MERALCO'S MAINTENANCE SCHEDULE VIA E-MAIL
    ------------------------------------------------------------------------------------------------------------------

    Attached is the schedule of our pre-arranged power interruptions for July 7 to 13 2014.  This serves as a general information guide and should not be directly construed as an interruption advisory to the e-mail recipients.

    Please call us at telephone numbers 16211 or 631-1111 for verification of power interruption schedule.

    If you wish to unsubscribe, please send us an e-mail and type in the word "Unsubscribe".

    Thank you very much.



    MAINTENANCE SCHEDULE

    To carry out necessary maintenance and upgrading works on various MERALCO distribution facilities, electric service will be temporarily interrupted on the following dates and places:


    MONDAY, JULY 7, 2014
    LAGUNA (CALAMBA)
      BETWEEN 9:00AM AND 2:00PM – PORTION OF CIRCUIT CANLUBANG 52XE
      Portion of Diversity Ave. and Nuvali Main Road from Avida Village Cerise Nuvali to and including Treveia Subd., Avida Estates Nuvali Subd., Montecito Estates Subd. and Avida Settings Nuvalis Subd.; Pasatiempo Clubhouse and Republic Wake Park in Bgys. Majada Labas and Canlubang.

      REASON:    Relocation of facilities in Bgys. Canlubang and Majada Labas, Calamba, Laguna.

    MONDAY TO TUESDAY, JULY 7 – 8, 2014
    BATANGAS PROVINCE (BATANGAS CITY; AND SAN PASCUAL)
      BETWEEN 11:00PM (MON., 07/07/14) AND 4:00AM (TUE., 07/08/14) – PORTION OF CIRCUIT BATANGAS 313SG
      Portion of Balagtas – Balete Barangay Road from Batangas City Diversion Road to and including Bgys. Balagtas, Banaba Center & East and Balete in Batangas City; Bgy. Banaba and Natunuan South in San Pascual.

      REASON:   To provide clearance for the installation of sub-transmission pole beside Balagtas Public Assistance, near Rotonda along Diversion Road cor. Batangas National Road, Batangas City.

    PASIG CITY (MAYBUNGA)
      BETWEEN 11:30PM (MON., 07/07/14) AND 4:30AM (TUE., 07/08/14) – PORTION OF CIRCUIT MANGGAHAN 43ZM
      Portion of Kamagong and Narra Sts. from Dr. Sixto Antonio Ave. to near C. Raymundo Ave. including ABQ Development Corp. in San Antonio Subd.
      Portion of Stella Maris Ave. from Dr. Sixto Antonio Ave. to near Indigo St. including Yellow St. in Stella Maris Subd.

      REASON:    Reconstruction of primary lines inside San Antonio Subd. and Stella Maris Subd. in Bgy. Maybunga, Pasig City.

    TUESDAY, JULY 8, 2014
    CAVITE (DASMARIÑAS CITY)
      BETWEEN 9:00AM AND 2:00PM – PORTION OF CIRCUIT GMA 46XF
      Bahay Karangalan, Bahay Katuparan and Mabuhay City 2000 Homes in Bgy. Paliparan 3.

      REASON:     Various maintenance works in Mabuhay City 2000 Homes in Bgy. Paliparan 3, Dasmariñas City, Cavite.

    WEDNESDAY TO THURSDAY, JULY 9 – 10, 2014
    TAGUIG CITY
      BETWEEN 11:30PM AND 11:59PM (WED., 07/09/14) AND THEN BETWEEN 4:00AM AND 4:30AM (THU., 07/10/14) – PORTION OF CIRCUIT TAGUIG 46ZL
      Portion of F. Manalo St. from near Ruhale St. to Gen. Luna St. in Bgy. Calzada.
      Portion of M. L. Quezon Ave. from Mastrili St. to Maria Rodriguez Tinga Ave. including Mahogany Place Phase 2 Subd., De-Va Ville Subd., Morning Sun Subd., Spring Lane Homes 2 Subd., St. Michael Subd., Victoria Compound and Bay Breeze Exec. Village in Bgys. Bambang, Calzada, Bagumbayan, Hagonoy, Tuktukan and Wawa.

      BETWEEN 11:30PM (WED., 07/09/14) AND 4:30AM (THU., 07/10/14) – PORTION OF CIRCUIT TAGUIG 46ZL
      Portion of Liwayway St. from Gen. Luna St. to Katipunan St. including Colegio de Sta. Ana in Bgy. Sta. Ana.

      REASON:     Replacement of rotten pole along Liwayway St. in Bgy. Sta. Ana, Taguig City.

    THURSDAY, JULY 10, 2014
    LAGUNA (CALAMBA CITY)
      BETWEEN 9:00AM AND 9:30AM AND THEN BETWEEN 1:30PM AND 2:00PM – PORTION OF CIRCUITS CALAMBA 31XO; AND CANLUBANG 47XE
      Portion of Calamba – Los Baños National Road from Belarmino St. to and including Spring Homes Subd., Lakeview Subd., Pamana Letran Homes Phases 1 & 2, Tierra Hermosa Subd., Belarmino 1 Subd., Lakeview Homes Phases Subd. 1 , 2 & 3, Lazaro Subd., Watawat Ng Lahi Cpd., Maria Salome Subd., South Meadows Subd., Villa Remedios East and West Subd. in Bgys. Bucal, Halang, Real, Poblacion, Lecheria and Parian.

      BETWEEN 9:00AM AND 2:00PM – PORTION OF CIRCUITS CALAMBA 31XO; AND CANLUBANG 47XE
      Portion of Calamba – Los Baños National Road from Purok IV to and including Indigo Bay Subd., Barreto Subd., Bayview Subd., Gemsville Subd., Laguna Hills Subd., Lakeview Subd., South Sppring Villas, Vanessa Homes Subd., Lago Vista Subd., Miramonte Subd., Mount View Subd., Nayong Maharlika Village, Northville Subd., Solemar Del Pansol Subd. and Villa Pansol in Bgys. Bagong Kalsada, Bucal, La Mesa and Pansol.

      REASON:   Relocation of facilities affected by DPWH road widening project along National Road in Bgy. Bucal, Calamba City, Laguna.
    CAVITE (TRECE MARTIRES CITY)
      BETWEEN 9:00AM AND 2:00PM – PORTION OF CIRCUIT TMC II 45WA
      Portion of Governor Drive from near Meralco – TMC II substation in Bgy. Tanauan, Tanza to Trece – Martires City – Tanza National Road including West Plains Subd., La Trinidad Subd., Pasong Baka, Elysian Fields Subd. and Don Bosco Executive Subd. in Bgys. Cabuco, De Ocampo and San Agustin.

      REASON:     Replacement of rotten cross arms along Governor Drive in Bgys. Cabuco and San Agustin, Trece Martires City, Cavite.
    FRIDAY, JULY 11, 2014
    CAVITE
      BETWEEN 9:00AM AND 10:00AM AND THEN BETWEEN 3:00PM AND 4:00PM – THE WHOLE OF CIRCUIT TERNATE 31ZO
      The whole of Gen. Emilio Aguinaldo except Bgys. Narvaez and A. Dalusag.
      The whole of Magallanes.
      The whole of Maragondon except Bgys. Mabato, Tulay Silangan, Kaylangis and Mabilog.
      Portion of Capt. A. Rillo St. and Antero Soriano Highway from Meralco – Ternate substation near Ternate – Maragondon Municipal boundary  to and including Medicare Community Hospital, Naic Ice Plant & Cold Storage, San Lorenzo Ruiz Hospital, Naic Doctor's Hospital and Naic Municipal High School; Bgys. Munting Mapino, Silangan Ibayo, Calubcob, Halang, Palangue-1, Palangue-3, Malainen, Molino, Malainen – Luma and Muzon in Naic.
                 
      REASON:    Preventive maintenance and testing works inside Meralco – Ternate substation.

    FRIDAY TO SATURDAY, JULY 11 – 12, 2014
    LAGUNA (CALAMBA)
      BETWEEN 11:00PM AND 11:30PM (FRI., 07/11/14) AND THEN BETWEEN 3:30AM AND 4:00AM (SAT., 07/12/14) – PORTIONS OF CIRCUIT CANLUBANG 45XE
      Portion of South Luzon Expressway (SLEX) West Service Road from near Batino Exit to Real Road including SLEX Calamba Toll Plaza in Bgys. Batino and Prinza.
      Portion of Real Road and Calamba – Sto. Tomas National Highway from South Luzon Expressway (SLEX) West Service Road to near Toyota Calamba in Bgys. Real, Tulo and Turbina.
      Portion of Calamba – Sto. Tomas National Highway from Tulo Elementary School to Lepanto Ceramics Plant including Ashton Fields Subd., The Homelands Subd., YMTI Realty Eco-Zone Compound, Lajara Compound, Purok 6; Makiling Drive; Metrobank, Trellis Pocket Center, Yazaki - Torres Technology Center, Makiling Conference Center, Laguna Hills Study Camp, TNC Chemicals, Jentec Cold Storage, Genuino Ice Plant and HI 5 Innotek Solutions in Bgys. Makiling, Putting Lupa and Tulo.
      Ionics EMS Inc., Aries 1400 Bldg., Miyoshi Technologies and 7-11 Store in Carmelray Industrial Park, Bgy. Tulo.
      Portion of Makiling, Ayala Greenfield and Spine Roads from Calamba – Sto. Tomas National Highway to and including Ayala Greenfield Estates Subd., Acacia Park Homes Subd. Phases 1 & 2; and Calamba Steel Center in Bgys. Kamaligan, Makiling, Maunong and Saimsim.

      BETWEEN 11:00PM (FRI., 07/11/14) AND 4:00AM (SAT., 07/12/14) – PORTION OF CIRCUIT CANLUBANG 45XE
      Portion of Real Road and Calamba – Sto. Tomas National Highway from Toyota Calamba to near Tulo Elementary School including Glenwood Park Subd.; Bureau of Jail Management and Penology (BJMP), Jollibee, Mang Inasal, Mercury Drug, Mitsubishi Motors, CAYC Shell Gas Station and Pacific Yeast Manufacturing in Bgys. Real, Tulo and Turbina.

      REASON:    Reconstruction and replacement of primary facilities along Calamba - Sto. Tomas National Highway in Bgys. Real, Tulo and Turbina in Calamba, Laguna.

    SUNDAY, JULY 13, 2014
    BATANGAS PROVINCE (BATANGAS CITY; AND SAN PASCUAL)
      BETWEEN 1:00AM AND 5:00PM – THE WHOLE OF CIRCUITS NGCP - BATANGAS – BOLBOC 58BS; NGCP - BOLBOC 33ZZ AND 32ZZ; AND MAHABANG PARANG 32WZ
      Cocochem Agro-Industrial Park in Bgy. San Pascual, San Pascual.
      Bgys. Soro-soro Karsada, Bukal, Concepcion and Mahabang Parang in Batangas City.

      REASON:      NGCP Job:
        1. Replacement of rotten pole & cross-arms along Batangas City National Road in Batangas City.
                Meralco Job:
          2. To provide safe clearance during the erection of self-support steel pole and conductor stringing along Diversion Road and National Road, Batangas City.
    3. Maintenance works inside NGCP Bolboc substation. 
      MERALCO exerts all efforts to restore electric service as scheduled. However, there are instances when due to unavoidable circumstances, restoration may extend beyond the published schedule.
      For more information, please contact our CALL CENTER at telephone no. 16211 / 631-1111, fax no. 1622-8554 / 632-8554, or e-mail address callcenter.tech.assist@meralco.com.ph. For faster resolution of inquiries, please use the Bill ID Number or Service Identification Number (SIN) indicated in your electric bills.
      For those who prefer to receive this schedule via e-mail, simply write to us at callcenter.tech.assist@meralco.com.ph and type in the phrase "Request for weekly schedule".



      VIEW YOUR BILL ON LINE. VISIT OUR WEBSITE!
      www.meralco.com.ph



      Privileged/Confidential information contained in this e-mail and its attachment/s is intended solely for the use of the addressee and is not meant for reproduction, disclosure and distribution to others without previous authorization from Meralco or its authorized representative.  If erroneously sent or received, please do not open and delete the same from your system.  Unless, otherwise specifically stated and confirmed by the authorized representative of Meralco, the opinions and views that may be contained therein are personal to the sender.