Attached is the schedule of our Pre-arranged Power Interruptions (PPI) for March 28 to April 3, 2016.  This serves as a general information guide and should not be directly construed as an interruption advisory to the e-mail recipients.

Please call us at telephone numbers 16211 or 631-1111 for verification of power interruption schedule.

If you wish to unsubscribe, please send us an e-mail and type in the word "Unsubscribe".

Thank you very much.



MAINTENANCE SCHEDULE

To carry out necessary maintenance and upgrading works on various MERALCO distribution facilities, electric service will be temporarily interrupted on the following dates and places:


MONDAY TO TUESDAY, MARCH 28 – 29, 2016
*CAVITE (DASMARIÑAS CITY)
    BETWEEN 11:00PM (MON., 03/28/16) AND 5:00AM (TUE., 03/29/16) – PORTION OF CIRCUITS ABUBOT 37XZ; AND DASMARIÑAS 42DA
    Portion of Congressional Ave. (DBB Highway)from Patch Village in Bgy. Sta. Lucia to and including Sitio Talisayan, Sitio Pansol, Talisayan Village, Bahay Pangarap, Bautista Property Phase II Subd., City Homes – Dasmariñas Subd., University Hills Subd., Victoria Reyes Property, Umakap Ka Compound, Windward Hills Subd., Town & Country Subd., Ilano Compound, De La Salle University Compound, Acacia Homes Subd, Tierra Verde Residences, Windsor Subd. and Dexterville Royale Subd. in Bgys. Burol I – III, Fatima I – III, Luzviminda I – II, Pag – Asa, San Andres I – II, San Francisco I – II, San Mateo, San Nicolas I – II, San Roque, San Simon, Sta. Cristina I – II, Emmanuel Bergado I – II, San Antonio De Padua I – II, San Juan, San Lorenzo Ruiz I – II, San Luis I – II, San Manuel II, Sta. Cruz I – II, Sta. Fe and Sta. Maria.
     
    REASON:    Replacement of poles and line reconductoring works along Mangubat Ave. in Dasmariñas City, Cavite.

TUESDAY, MARCH 29, 2016
LAGUNA (CALAMBA)
    BETWEEN 8:00AM AND 8:30AM AND THEN BETWEEN 3:30PM AND 4:00PM – PORTION OF CIRCUIT CALAMBA 413CMB
    Portion of Makiliing - Real Road from Lyceum of the Philippines – Calamba Campus to near Ciudad Verde Subd. in Bgy. Makiling.

    REASON:     Line maintenance works along Makiling – Real Road in Bgy. Makiling, Calamba, Laguna.

TUESDAY TO WEDNESDAY, MARCH 29 - 30, 2016
RIZAL (ANTIPOLO CITY)
    BETWEEN 11:00PM (TUE., 03/29/16) AND 5:00AM (WED., 03/30/16) – PORTION OF CIRCUIT DOLORES 45XM
    Portion of M. L. Quezon St. from M. santos St. St. to near M. Gatbalayan St. including Jollibee Restaurant, Gems Foodmart, Mercury Drug Store, World Citi Colleges - Antipolo and Antipolo Public Market in Bgy. San Roque.
    Portion of J. Sumulong St. from Villa Carmen Subd. to San Jose St. including F. Dimanlig and J. Torres Sts.; Super Palengke,  in Bgys. San Roque and San Jose.

    REASON:     Various line maintenance works along M. L. Quezon St. in Bgy. San Roque, Antipolo City, Rizal.

PARAÑAQUE CITY
    BETWEEN 11:30PM (TUE., 03/29/16) AND 4:30AM (WED., 03/30/16) – PORTION OF CIRCUIT BF-PARAÑAQUE 42WU – PARAÑAQUE 45ZJ
    Portion of Manila – Cavite Expressway (CAVITEX) from NAIA Road to MMDA Sewerage Plant including Seaside Drive St.; KFC Restaurant, Tambo Barangay Hall and LBC Express in Bgy. Tambo.

    REASON:     Relocation of poles affected by DPWH road widening project along Manila – Cavite Expressway (CAVITEX) in Bgy. Tambo, Parañaque City.

WEDNESDAY, MARCH 30, 2016
BULACAN (BALAGTAS)
    BETWEEN 12:01AM AND 12:30AM AND THEN BETWEEN 5:30AM AND 6:00AM – PORTION OF CIRCUIT STA. MARIA 43YU
    Portion of Balagtas – Provincial Road from St. Peter Subd. to near Balagtas – Plaridel Road including Rocka Compound, Villa Juliana Subd., Virgen Milagrosa Homes Subd.;  Windmill St.; Success Wood Industry and Style & Décor Co. in Bgys. Borol 2nd and Pulong Gubat.
    MNTC Toll Plaza along Plaridel – Balagtas Bypass Road in Bgy. Borol 2nd.

    BETWEEN 12:01AM AND 6:00AM – PORTION OF CIRCUIT STA. MARIA 43YU
    Portion of Balagtas – Plaridel Provincial Road from Balagtas – Pandi Road to near Balagtas – Plaridel municipal boundary including Divine Grace Village II, Northville Subd. Phases 1 & 6-B, Sitio Galas; NIA Road and Galvez St; Andrew's Meat Products, Poly Steel Tube Mfg., Adze Enterprises and La Primera Pollo Inc. in Bgys. Pulong Gubat and Santol.
    Portion of Balagtas – Pandi Road from Balagtas – Plaridel Provincial Road to Roxas St. including Jordan Valley Subd. in Bgys. Santol and Pulong Gubat.

    REASON:     Urgent replacement of hazardous poles, line reconductoring works and installation of additional lightning protection devices along Balagtas - Plaridel Provincial Road in Bgy. Santol, Balagtas, Bulacan.
CALOOCAN CITY
    BETWEEN 9:00AM AND 2:00PM – PORTION OF CIRCUIT KAYBIGA 45YX
    Blocks 1, 16, 27, 32 and 36 in Celna Homes 2, Bgy. Kabatuhan.

    REASON:     Line maintenance works inside Celina Homes 2 in Bgy. Kabatuhan, Caloocan City.
LAGUNA (STA. ROSA)
    BETWEEN 9:00AM AND 2:00PM – PORTION OF CIRCUIT LIIP 425WM
    South Hampton Subd. in Bgy. Balibago.

    REASON:     Relocation of primary facilities along Queensway Ave. in South Hampton Subd., Bgy. Balibago, Sta. Rosa, Laguna.

WEDNESDAY TO THURSDAY, MARCH 30 – 31, 2016
VALENZUELA CITY
    BETWEEN 11:00PM (WED., 03/30/16) AND 5:00AM (THU., 03/31/16) – PORTION OF CIRCUIT MEYCAUAYAN 52YM
    Portion of Punturin – Lawang Bato Road from Kabesang Porong St. to near Yardly St. including Pearl Island Compound, Cabral Industrial Subd., Sta. Lucia Village Phases 3, 4 & 6; P. Faustino St.; Buffalo Steel, Topwell Plastic, Uni Lucky Mfg., TYP Plastics, GYP Junk Shop, Plastic Consumer Corp., Aimway Plastic & Printing, Amtes Corp., Ayroso Wire Master, Bedrock Marketing, Century Glass Center, Eternal Industry Enterprises, Fiberworld Inc., Fompac Plastic, Good Earth Chemical, Hyper Pack Plastic Industries, MBP Star Corp., Mitsuboshi Belting, Newfoods International, Plastic Technobag, Plastmack, Royal Pinnacle Estate, Royu Industrial, Plastmack Inc., T.L.A. Corp., Unifoam Enterprises, Uniroof Steel, Chatterton Corp., Lamitek Systems, McKay Mfg., Uygawani Steel, Keiser Packing Solutions Inc. and Consumer Packaging Products  in Bgy. Punturin.

    REASON:     Relocation of pole and installation of additional lightning protection devices along Sapang Bakaw, Daang Bato, Malinis Centro and Lawang Bato Roads in Bgy. Punturin, Valenzuela City.
*CAVITE (DASMARIÑAS CITY)
    BETWEEN 11:00PM (WED., 03/30/16) AND 4:00AM (THU., 03/31/16) – PORTION OF CIRCUITS IMUS 422WK AND 423WK
    Portion of Molino – Paliparan Road from Gov. Mangubat Ave. (Salitran – Salawag Road) in Bgy. Salawag, Dasmariñas City to Avenida Rizal including Camella Homes Springville Subd., Ponticelli I Subd., Ponticelli Gardens Subd., Ponticelli Hills Subd., Camella Springville Heights Subd.,  Camella Cerritos Subd., Cerritos Heights Subd., Cuevasville Subd., Duplex Subd., Elisa Homes Subd., Georgetown Heights Subd., Mary Homes Subd., Meadow Park Subd., Melissa Homes Macaria Homes and Summerhills Subd. in Bgys. Molino II, III, IV and VI, Bacoor City; and Promenade Residences in Bgy. Salawag, Dasmariñas City.
REASON:    Relocation of primary facilities affected by DPWH roadwidening project along Molino – Paliparan Road in Bgy. Molino IV, Bacoor City, Cavite.
THURSDAY, MARCH 31, 2016
PARAÑAQUE CITY
    BETWEEN 12:01AM AND 5:00AM – PORTION OF CIRCUIT PARAÑAQUE 47ZJ
    Portion of Quirino Ave. from Meralco - Parañaque substation along Bayside Court  to NAIA Road including M. Delos Santos St. in Bgy. Tambo.

    REASON:     Relocation of primary facilities along Quirino Ave. in Bgy. Tambo Parañaque City.
MUNTINLUPA CITY
    BETWEEN 8:00AM AND 1:00PM – PORTION OF CIRCUIT AYALA ALABANG 425WR
    Portion of Caliraya St. from University Drive St. to San Bernardino St. including Agno, Ambuklao, La Mesa, Ma. Cristina, Pantabangan and San Juanico Sts. including Our Lady of the Star Chapel in Ayala Alabang Village, Bgy. New Alabang Village.

    REASON:     Line reconductoring work along along Ma. Cristina and Caliraya Sts. in Ayala Alabang Village, Bgy. New Alabang Village, Muntinlupa City.

SUNDAY, APRIL 3, 2016
MANILA (TONDO)
    BETWEEN 8:00AM AND 8:30AM AND THEN BETWEEN 12:30PM AND 1:00PM – PORTION OF CIRCUIT NORTH PORT 406H
    Portion of Dagupan and Gregoria Perfecto Sts. from Tayuman St. to Moriones St. including Balaya, Arqueros, Bucaneg, Cabezas, Deodato, Endaya, Fullon, Gabriela, Hamabar, Mercado, Jose Basa, R. Almario and Coral Sts.

    BETWEEN 8:00AM AND 1:00PM – PORTION OF CIRCUIT NORTH PORT 406H
    Portion of Juan Luna St. from  Corcuera St. to Nicodemus St. including Lecheros Tello and Peñalosa Sts.
    Portion of Nicolas Zamora St. from Corcuera St. to and including Concha, Aguila, Pavia, Mejorada, Perla, Pilapil, Coral, Nicodemus, Pacheco, Pitong Gatang, Panday Pira, Amarlanhagui and Baltazar Sts.

    REASON:     Line reconductoring works along Nicolas Zamora and Juan Luna Sts. in Tondo, Manila.

MAKATI CITY
    BETWEEN 8:00AM AND 8:30AM AND THEN BETWEEN 12:30PM AND 1:00PM – PORTION OF CIRCUIT NEW ROCKWELL 442VV
    Portion of J. P. Rizal St. from Guadalupe Interchange Cloverleaf to and including Camia, Progreso, Carballo, Trinidad, Bernardino, Coronado, Gonzales and Progreso II Sts.; Caltex Gas Station, Guadalupe Viejo Elementary School,  Shell Gas Station, PR Enterprises and Makati Youth Center Headquarters in Bgy. Guadalupe Viejo.
    Portion of Epifanio Delos Santos Ave. (EDSA) from Guadalupe Interchange Cloverleaf to and including Iran Embassy Cultural Section, State Condominium V, San Carlos Seminary, Loyola Memorial Chapel and Our Lady of Guadalupe Minor Seminary in Bgy. Guadalupe Viejo.

    REASON:     Line reconductoring works along Estrella St. in Bgy. Guadalupe Viejo, Makati City.

*CAVITE (GEN. TRIAS; NOVELETA; ROSARIO AND TANZA)
    BETWEEN 9:00AM AND 10:00AM AND THEN BETWEEN 2:00PM AND 3:00PM – THE WHOLE OF CIRCUIT ROSARIO 42RS
    Portion of Gov. Ferrer, Dulong Bayan and Gen. Antonio Sts. from Gen. Trias Drive to and including Bgys. Bacao 1 & 2, Pinagtipunan, San Juan and Tejero in Gen. Trias.
    Portion of Antero Soriano Highway and New C- 6 Road (EPZA Rosario – Bacao Diversion Road) from Tanza Municipal Hall to Petron gas station; Valley Field Subd., Norvioric Subd., Costa Verde Subd., Em's Barrio, Graceville Subd. and Ricafrente Compound in Bgys. Tejeros Convention, Silangan 2, and Bagbag 2 in Rosario; St. Anthony Subd. and Familyville Subd. in Bgys. Amaya 1, Bucal, Daang Amaya 1, Daang Amaya 3 and town proper in Tanza.

    REASON:    Preventive maintenance and testing works inside Meralco – Rosario substation.

    MERALCO exerts all efforts to restore electric service as scheduled. However, there are instances when due to unavoidable circumstances, restoration may extend beyond the published schedule.
    For more information, please contact our CALL CENTER at telephone no. 16211 / 631-1111, fax no. 1622-8554 / 632-8554, or e-mail address callcenter.tech.assist@meralco.com.ph. For faster resolution of inquiries, please use the Bill ID Number or Service Identification Number (SIN) indicated in your electric bills.
    For those who prefer to receive this schedule via e-mail, simply write to us at callcenter.tech.assist@meralco.com.ph and type in the phrase "Request for weekly schedule".



    VIEW YOUR BILL ON LINE. VISIT OUR WEBSITE!
    www.meralco.com.ph



    *Additional PPI

    Privileged/Confidential information contained in this e-mail and its attachment/s is intended solely for the use of the addressee and is not meant for reproduction, disclosure and distribution to others without previous authorization from Meralco or its authorized representative.  If erroneously sent or received, please do not open and delete the same from your system.  Unless, otherwise specifically stated and confirmed by the authorized representative of Meralco, the opinions and views that may be contained therein are personal to the sender.